Case study · General contractor

Hickory: Trio

Project: Trio
Facade tracking

Trio in Box Hill had two towers with two manufacturers making facade panels at the same time, and it was hard to tell which panels belonged to which. Hickory used Matrak to assign every curtain wall panel to its manufacturer, traced delayed or defective panels back to the right one, and was able to offer the client earlier handover dates.

Untitled design (2)

Challenge, solution and result

Key Challenges

  • Hickory's Trio project consisted of two towers with two different manufacturers manufacturing facade panels concurrently. It became hard to manage and understand which panels belonged to which this cost Hickory additional time when needing to follow up with manufacturers in the event panels were defective or needed to be re-ordered.

Solution

  • Matrak was used to assigned every curtain wall panel for each tower to their respective manufacturing suppliers.
  • Hickory was able to track the right panels back to the right manufacturers in case of the event that items were delayed or defective

Result

  • Hickory was able to offer the client earlier handover dates utilizing Matrak to seamlessly run multiple manufacturers on the same job concurrently
  • Able to easily generate detailed shipping reports, drilled down to the specific panel

Trio is a premier mixed-use development compromising of 3 towers overlooking Box Hill, VIC Australia..

The 6 level podium occupying 488 apartments, holds two towers which are residential apartments and a third tower housing independent living apartments along with a two-level childcare facility.

Hickory uses Matrak to track the manufacturing of all facade panels for Trio, helping the teamseamlessly run multiple manufacturers on the same job, concurrently.

The Problem

The build consisted of two towers with two different manufacturers manufacturing facade panels concurrently. It became hard to manage and understand which panels belonged to which this cost Hickory additional time when needing to follow up with manufacturers in the event panels were defective or needed to be re-ordered.

The Solution

Matrak was used to assigned every curtain wall panel for each tower to their respective manufacturing suppliers.

Hickory was able to track the right panels back to the right manufacturers in case of the event that items were delayed or defective

The Result

Hickory was able to offer the client earlier handover dates utilizing Matrak to seamlessly run multiple manufacturers on the same job concurrently

Able to easily generate detailed shipping reports, drilled down to the specific panel

Modules used on this project.

Each one has its own page with the price and a sample project. Add them to your Matrak and see what it costs for your job.

Your project, tracked like theirs.

Start free with your own company, up to 2,000 items, or build your Matrak: pick your modules and see your price. Prefer a walkthrough? Book a demo.

Free for your own company, up to 2,000 items, no card needed · Modules for one project or every project · AI Takeoff from C$89 a trade