Construction daily report template

The Matrak dashboard for a project: materials, tasks, members and contractors, with site progress below, the numbers a construction daily report is written from

A construction daily report template is a short form the site supervisor fills in at the end of each day: the weather, who was on site, what work was done and where, what was delivered, what held the job up and what was instructed. Our free Excel version is below.

The same record is called a construction daily log in the United States, a daily site report in the UK and a site diary in Australia. For why it matters and how long to keep it, see the construction site diary.

What goes in a construction daily report?

SectionWhat to fill in
HeaderProject, date, report number, who wrote it
WeatherMorning and afternoon, temperature, time lost
Crews on siteEach company, how many workers, where they worked
Work doneThe activity, the location and how far it got
DeliveriesWhat arrived, from whom, the docket number, any damage
Plant and equipmentMajor plant used, breakdowns and standing time
Delays, issues and incidentsWhat stopped or slowed work, for how long, who was told
Instructions and visitorsVerbal instructions, inspections, who came to site
PhotosThree to ten, each with a location
Matrak construction progress tracking software: a progress grid of eight levels by trade, with complete, in progress and issue cells, beside the phone app the trades update it from

Construction daily report example

One day on a mid-rise apartment job. Notice the times, the quantities and the names.

SectionEntry
WeatherFine until 2:15 pm, then rain. 1.5 hours lost, external trades only
Crews on siteConcrete 9, formwork 12, electrical 6, plasterer 8
Work doneLevel 6 slab poured, 180 m3, finished 1:40 pm. Level 2 linings fixed in 6 of 12 apartments
DeliveriesPlasterboard, 14 pallets. Two sheets damaged on pallet 9, photo 4
PlantTower crane stood down 2:15 pm to 3:45 pm
DelaysLevel 4 rough-in waiting on an answer about the riser location. Half a day, two workers
InstructionsClient's representative asked for the Level 2 corridor ceiling to be lowered 50 mm. Told to confirm in writing
InspectionsEngineer inspected Level 6 reinforcement at 7:10 am and released the pour

The record of work done, written by the work. With Matrak Progress, trades mark work done on their phone and the day's progress is already there.

Construction daily log or daily report?

They are the same form. Some US contractors use daily log for the superintendent's own running record and daily report for the copy sent to the owner. Subcontractors send their own daily report to the general contractor: crew, work done, and anything that held them up.

How to fill it in in ten minutes

  1. Start it at 7 am. Weather and crews go in at the morning walk, not at 5 pm.
  2. Note things as they happen. A delivery, a visitor, an instruction: one line each, with the time.
  3. Take the photos on your afternoon walk. The same spots each day show progress best.
  4. Write facts, not opinions. 'Formwork crew left at 1 pm' not 'formworkers slack again'.
  5. Finish before you leave. Tomorrow you will not remember today.

Free construction daily report template

Take our construction daily log template for Excel: the sections above on a blank form that prints on A4, with the example filled in on a second sheet. In the UK it works as a site report template without changing a word. No sign-up.

Crews on siteWorkersWhere they worked
Company or trade
Company or trade
Company or trade

Common mistakes with daily reports

  • Written on Friday for the whole week. Five days from memory is one day of facts.
  • 'Work continued'. Where, by whom, how far? If it cannot be checked, it is not a record.
  • Delays with no cause. 'Lost two hours' helps nobody. 'Lost two hours waiting for the pump' supports a claim.
  • Verbal instructions left out. The instruction you did not write down is the variation you will not be paid for.
  • Photos with no location. Name the level and the room.

A late instruction or a change to the drawings belongs in a variation as well: see construction variations.

A Matrak delivery report: each delivery shown as booked, packed, in transit, delivered or rejected, the deliveries line of a daily report

A daily report that fills itself in

Matrak ProgressPaper or Excel form
A dated record of work done, by locationYesYes
Trades mark work done on their own phoneYesNo
Progress shown for every level and tradeYesNo
Photos kept against the item or the roomYesNo
Who recorded each update, and whenYesNo
Today's site progress report, with nothing to typeYesNo

How Matrak does it. Trades mark work done on their phone as they go, so the board is always today's site progress report, level by level and trade by trade. Your daily report can stick to weather, delays and instructions. Matrak Progress is $12,000 for one project for a year (A$, plus GST).

Why it takes nobody's evening. The levels, areas and trades come from drawings fetched from Procore, Aconex and Autodesk and from your programme, and every update sits in a full audit history.

Looking at site reporting tools? See how Matrak compares. For the weekly or monthly version of this record, use the construction progress report template.

Frequently asked questions

What is a construction daily report?

A construction daily report is a dated record of one day on site: weather, crews, work completed, deliveries, equipment, delays, instructions and visitors. It is written by the person running the site and kept as part of the project record.

Who fills in the daily report?

The site supervisor, foreman or superintendent who ran the site that day. Each subcontractor's supervisor usually fills in one for their own crew and sends it to the head contractor.

What is the difference between a daily report and a progress report?

A daily report records what happened on one day. A progress report compares where the job is with where the programme says it should be, usually each week or month, and is written for the client.

How long should daily reports be kept?

For at least as long as a claim can be made on the project, which can be many years after completion. Check your contract and get advice on the time limits where you build.

Should subcontractors submit daily reports?

Yes, if the subcontract asks for it, and it is good practice anyway. A subcontractor's own record of crew numbers, work done and hold-ups is their best evidence if a delay or a claim is disputed.

Put this to work on your job.

Pick the modules you need, see your price and share it with whoever signs it off. No call needed.

Read enough? See it on your job.

Start free with your own company, up to 2,000 items, or build your Matrak: pick your modules and see your price. Prefer a walkthrough? Book a demo.

Free for your own company, up to 2,000 items, no card needed · Modules for one project or every project · AI Takeoff from A$89 a trade