Construction progress report template

A construction progress report in Matrak: a grid of eight levels by trade showing complete, in progress and issue cells against the programme line, beside the phone app

A construction progress report template is a set layout for telling the client and the project team where the job is against the programme: percent complete by area and trade, milestones, what is late and why, and what happens next. It is issued every week or every month. Our free Excel template is below.

What is in a construction progress report?

SectionWhat it showsTip
SummaryOverall percent complete, planned against actual, and the forecast finishOne line a director can repeat
Progress by area and tradePlanned and actual percent for each level and tradeThis is the page people turn to
MilestonesBaseline date, forecast date and days lateNever drop a late milestone off the list
Delays, issues and risksThe cause, the days at risk, the action and its ownerA cause, not a complaint
Next periodWhat starts and finishes before the next reportAnd what each activity needs first
QualityInspections done, open defectsCounts, not adjectives
PhotosThe same viewpoints every periodProgress shows when the angle does not change
The Matrak progress tracker: every level's status across each trade stage, from not started to in progress, live from site

How to measure percent complete

Percent complete is only worth reporting if two people would get the same number.

MethodHow it worksBest for
Units completeRooms tiled divided by rooms to tileRepeated work: apartments, floors, panels
StepsEach step is worth a share: framed 30%, lined 40%, set 30%Work with clear stages
0, 50, 100Nothing until started, half until finishedShort activities
By eyeSomeone estimates itNothing. This is where 90% complete lasts six weeks

Stop chasing the site for updates. With Matrak Progress the report fills itself in as trades mark work done.

Construction progress report example

Week 14 of a fitout, three levels, counted by apartment.

LevelTradePlannedActualVarianceComment
Level 1Wall and ceiling linings100%100%0Complete
Level 2Wall and ceiling linings100%85%-15Started late after the services inspection was redone
Level 2Waterproofing50%20%-30Waiting on linings
Level 3Services rough-in80%90%+10Ahead
Level 3Wall framing100%100%0Complete

Read it across: Level 2 linings is the problem and waterproofing is the knock-on. The summary line writes itself: 'Level 2 is a week behind after an inspection was redone. A second lining crew starts Monday.'

How to write the summary line

Most readers stop after the summary, so it carries the whole report in three parts:

  1. Where the job is. One number against the plan: 62% complete against 68% planned.
  2. What is late, and why. The cause in plain words, not 'various delays'.
  3. What happens next. The action, who owns it and the date.

Construction progress reporting: weekly or monthly?

Weekly reportMonthly report
ReaderSite team and subcontractorsClient, financier, directors
DetailBy room and taskBy level, trade and milestone
LengthOne pageThree to six pages with photos
Goes withThe lookaheadThe progress claim

The monthly report and the claim should tell the same story: see the progress claim template. The dates it is measured against come from the construction programme, and the day-by-day facts from the site diary.

Free construction progress report template

Take our construction progress report template for Excel. Type planned and actual percent and the variance works itself out. Type a baseline and a forecast date and the days late work themselves out. The example above is filled in on a second sheet. No sign-up.

Area or levelTrade or activityPlanned %Actual %VarianceComment
Worked out for you
Worked out for you
Worked out for you

Common mistakes in progress reports

  • Percent by eye. Count finished rooms.
  • Good news only. A report that never shows a delay is not believed when it finally does.
  • Late milestones quietly re-dated. Keep the baseline date beside the forecast.
  • Problems with no action. Every issue needs an owner and a date.
  • Three days to write. By the time it is issued, it describes last week.
A Matrak tiling progress report: each apartment's status with inspection results marked pass, fail or N/A, and its start and due dates

A progress report that fills itself in

Matrak ProgressReport in Excel
Planned against actual for every level and tradeYesYes
Filled in by trades marking work done on their phoneYesNo
Always today's numbersYesNo
Shows which trade is holding up the nextYesNo
Set up from your drawings and programmeYesNo
Takes nobody's FridayYesNo

How Matrak does it. Matrak Progress is set up from your drawings and your programme. Trades mark work done on their phone, so the board shows progress against the programme for every level and trade, today. $12,000 for one project for a year (A$, plus GST).

Why the numbers are believed. Each update is counted from the work itself and kept in a full audit history, and the drawings behind it are fetched from Procore, Aconex and Autodesk.

Choosing a progress tool? See how Matrak compares and read the best construction progress tracking software. For the day-by-day record, use the construction daily report template.

Frequently asked questions

What is a construction progress report?

A construction progress report tells the client and the project team where the job stands against the programme: percent complete by area and trade, milestone dates, delays and their causes, and the work planned for the next period.

How do you calculate percent complete?

Count finished units against the total: 17 of 20 apartments lined is 85%. For work with stages, give each stage a share. Avoid estimating by eye, because two people will give two answers.

How often should progress be reported?

Weekly to the site team and subcontractors, and monthly to the client, usually with the progress claim. Your contract may set the dates and the format.

Who prepares the progress report?

The head contractor's project manager or site manager, using progress measured on site and dates from the planner. Subcontractors report their own progress to the head contractor.

What is the difference between a progress report and a progress claim?

A progress report says how much work is done against the programme. A progress claim asks to be paid for that work. They should agree, and the report is often the evidence for the claim.

Put this to work on your job.

Pick the modules you need, see your price and share it with whoever signs it off. No call needed.

Read enough? See it on your job.

Start free with your own company, up to 2,000 items, or build your Matrak: pick your modules and see your price. Prefer a walkthrough? Book a demo.

Free for your own company, up to 2,000 items, no card needed · Modules for one project or every project · AI Takeoff from A$89 a trade