A construction progress report template is a set layout for telling the client and the project team where the job is against the programme: percent complete by area and trade, milestones, what is late and why, and what happens next. It is issued every week or every month. Our free Excel template is below.
What is in a construction progress report?
| Section | What it shows | Tip |
|---|---|---|
| Summary | Overall percent complete, planned against actual, and the forecast finish | One line a director can repeat |
| Progress by area and trade | Planned and actual percent for each level and trade | This is the page people turn to |
| Milestones | Baseline date, forecast date and days late | Never drop a late milestone off the list |
| Delays, issues and risks | The cause, the days at risk, the action and its owner | A cause, not a complaint |
| Next period | What starts and finishes before the next report | And what each activity needs first |
| Quality | Inspections done, open defects | Counts, not adjectives |
| Photos | The same viewpoints every period | Progress shows when the angle does not change |

How to measure percent complete
Percent complete is only worth reporting if two people would get the same number.
| Method | How it works | Best for |
|---|---|---|
| Units complete | Rooms tiled divided by rooms to tile | Repeated work: apartments, floors, panels |
| Steps | Each step is worth a share: framed 30%, lined 40%, set 30% | Work with clear stages |
| 0, 50, 100 | Nothing until started, half until finished | Short activities |
| By eye | Someone estimates it | Nothing. This is where 90% complete lasts six weeks |
Stop chasing the site for updates. With Matrak Progress the report fills itself in as trades mark work done.
Construction progress report example
Week 14 of a fitout, three levels, counted by apartment.
| Level | Trade | Planned | Actual | Variance | Comment |
|---|---|---|---|---|---|
| Level 1 | Wall and ceiling linings | 100% | 100% | 0 | Complete |
| Level 2 | Wall and ceiling linings | 100% | 85% | -15 | Started late after the services inspection was redone |
| Level 2 | Waterproofing | 50% | 20% | -30 | Waiting on linings |
| Level 3 | Services rough-in | 80% | 90% | +10 | Ahead |
| Level 3 | Wall framing | 100% | 100% | 0 | Complete |
Read it across: Level 2 linings is the problem and waterproofing is the knock-on. The summary line writes itself: 'Level 2 is a week behind after an inspection was redone. A second lining crew starts Monday.'
How to write the summary line
Most readers stop after the summary, so it carries the whole report in three parts:
- Where the job is. One number against the plan: 62% complete against 68% planned.
- What is late, and why. The cause in plain words, not 'various delays'.
- What happens next. The action, who owns it and the date.
Construction progress reporting: weekly or monthly?
| Weekly report | Monthly report | |
|---|---|---|
| Reader | Site team and subcontractors | Client, financier, directors |
| Detail | By room and task | By level, trade and milestone |
| Length | One page | Three to six pages with photos |
| Goes with | The lookahead | The progress claim |
The monthly report and the claim should tell the same story: see the progress claim template. The dates it is measured against come from the construction programme, and the day-by-day facts from the site diary.
Free construction progress report template
Take our construction progress report template for Excel. Type planned and actual percent and the variance works itself out. Type a baseline and a forecast date and the days late work themselves out. The example above is filled in on a second sheet. No sign-up.
| Area or level | Trade or activity | Planned % | Actual % | Variance | Comment |
|---|---|---|---|---|---|
| Worked out for you | |||||
| Worked out for you | |||||
| Worked out for you |
Common mistakes in progress reports
- Percent by eye. Count finished rooms.
- Good news only. A report that never shows a delay is not believed when it finally does.
- Late milestones quietly re-dated. Keep the baseline date beside the forecast.
- Problems with no action. Every issue needs an owner and a date.
- Three days to write. By the time it is issued, it describes last week.

A progress report that fills itself in
| Matrak Progress | Report in Excel | |
|---|---|---|
| Planned against actual for every level and trade | Yes | Yes |
| Filled in by trades marking work done on their phone | Yes | No |
| Always today's numbers | Yes | No |
| Shows which trade is holding up the next | Yes | No |
| Set up from your drawings and programme | Yes | No |
| Takes nobody's Friday | Yes | No |
How Matrak does it. Matrak Progress is set up from your drawings and your programme. Trades mark work done on their phone, so the board shows progress against the programme for every level and trade, today. $12,000 for one project for a year (A$, plus GST).
Why the numbers are believed. Each update is counted from the work itself and kept in a full audit history, and the drawings behind it are fetched from Procore, Aconex and Autodesk.
Choosing a progress tool? See how Matrak compares and read the best construction progress tracking software. For the day-by-day record, use the construction daily report template.
Frequently asked questions
What is a construction progress report?
A construction progress report tells the client and the project team where the job stands against the programme: percent complete by area and trade, milestone dates, delays and their causes, and the work planned for the next period.
How do you calculate percent complete?
Count finished units against the total: 17 of 20 apartments lined is 85%. For work with stages, give each stage a share. Avoid estimating by eye, because two people will give two answers.
How often should progress be reported?
Weekly to the site team and subcontractors, and monthly to the client, usually with the progress claim. Your contract may set the dates and the format.
Who prepares the progress report?
The head contractor's project manager or site manager, using progress measured on site and dates from the planner. Subcontractors report their own progress to the head contractor.
What is the difference between a progress report and a progress claim?
A progress report says how much work is done against the programme. A progress claim asks to be paid for that work. They should agree, and the report is often the evidence for the claim.