Construction site logistics plan

A site logistics plan in action in Matrak: a deliveries report counting loads booked, loaded, on the road, at the gate, unloaded and signed, beside the phone record for one delivery with its truck and gate

A site logistics plan, also called a construction logistics plan, is a marked-up drawing and a short set of rules that show how people, trucks, materials and waste get on, off and around a building site at each stage of the job: the gates, the truck routes, the unloading zones, the cranes and hoists, the storage areas and how deliveries are booked.

In the UK a construction logistics plan is often a planning condition and concentrates on truck movements to and from the site. In Australia much of the same ground sits in the construction management plan a council asks for. In the United States the site logistics plan is usually part of the bid.

What goes in a site logistics plan?

PartWhat to show on the drawingWhat to decide
Site boundary and gatesThe hoarding line, each gate and what it is forGate hours, and who controls each gate
Truck routesApproved roads to the site, turning paths, where trucks waitThe largest truck allowed, and the times trucks are not
Unloading zonesWhere each truck stopsCrane, forklift or by hand, and for how long
Cranes and hoistsPositions, reach and landing platformsBooking rules, and who has priority on pour days
Storage and laydownAn area for each trade, on the ground and on each floorThe most days anything may sit on site
PeopleWalking routes kept apart from vehicles, the site entryWhere workers and visitors come in
WasteBin positions and the route outCollection times that miss the delivery peaks
Neighbours and authoritiesRoad closures, footpath diversions, loading zonesPermits, noise hours, who tells the neighbours
StagesThe drawing redrawn for each stageThe date each stage's plan takes over
Matrak deliveries grouped by status: not started, booked, packed, in transit, rejected and delivered, with a count for each

What makes a construction logistics plan work?

Three pieces, and most plans only have the first.

  • The drawing. One marked-up site plan for each stage, on the wall at the gate.
  • The booking schedule. Every delivery on one list, with its slot, gate and unloading method.
  • The rules. What happens to a truck with no booking, and who decides.

Site logistics plan example, stage by stage

A mid-rise apartment building on a tight city site.

StageMain deliveriesUnloaded byPinch point
Excavation and basementSpoil out, concrete and reinforcement inTrucks on the ramp, a pump at the kerbTrucks queuing in the street
StructureConcrete, formwork, reinforcement, precastTower cranePour days: nothing else can be unloaded
FacadePanels and windows on framesTower crane, straight to the floorNowhere to store, so each load is called up for the day it is fixed
FitoutPlasterboard, joinery, tiles, appliancesHoist, by bookingHoist time
HandoverFurniture, final cleanGoods liftFinished floors and walls to protect

No wasted trips: the site is ready when the truck is. Matrak Logistics tracks every delivery from dispatch to the hoist.

The delivery booking rules

  1. Every delivery is booked. At least a day ahead, with a time slot, a gate and a truck type.
  2. The booking says how it is unloaded and where it goes. Level and zone, not 'site'.
  3. The crane or hoist is booked in the same line. A truck at the gate with no hoist is a truck in the street.
  4. Each trade gets tomorrow's list today. So someone is there to receive it.
  5. No booking, no entry. It only has to happen once.

What to order and when sits one step earlier, in the procurement schedule. The dates come from the construction programme, and the label on each load is covered in QR codes in construction.

Free site logistics plan template

Take our site logistics plan template for Excel: the nine parts above with room to write your rules, the stage example, and a delivery booking schedule with a status drop-down. Attach your marked-up site plan and it is ready to issue. No sign-up.

DateTime slotGateSupplier or tradeLoadUnloaded byGoes to
Mon7:00 to 8:001Facade contractor16 facade panels on two framesTower craneLevel 8, north face
Mon10:00 to 10:302Plasterer14 pallets of plasterboardForklift, then hoistLevel 3, zone B

Common mistakes in logistics plans

  • One drawing for the whole job. The gate that works for excavation is under the hoist by fitout.
  • A plan without a booking list. The drawing says where. Only the list says when.
  • Storage for everyone, forever. Give each trade an area and a number of days.
  • The hoist left out. On a tower, hoist minutes are the scarcest thing on site.
  • Suppliers never told. The driver is the person who most needs the plan.
A Matrak delivery report: each delivery listed as booked, packed, in transit, delivered or rejected

Every delivery tracked to the hoist

Matrak LogisticsWhiteboard or spreadsheet
A list of deliveries with dates and gatesYesYes
One delivery schedule for the site, the supplier and the freight companyYesNo
Each load tracked: booked, loaded, on the road, at the gate, unloadedYesNo
A signed delivery recordYesNo
Loads made up from the products tracked off your drawingsYesNo
Dates taken from your programmeYesNo

How Matrak does it. Matrak Logistics gives the site, the supplier and the freight company one delivery schedule. Each load is tracked from booked and loaded to at the gate, unloaded and signed, so the hoist is booked for what is on the truck. $3,600 for one project for a year (A$, plus GST).

Why it is not a second spreadsheet. Loads are made up from the products already tracked off your drawings, which are fetched from Procore, Aconex and Autodesk, with dates from your programme and a full audit history of every change.

Tracking the products as well as the trucks? See Matrak Supply chain and Matrak for logistics. Weighing up systems? See how Matrak compares.

Frequently asked questions

What is a site logistics plan?

A site logistics plan shows how a construction site will work day to day: where the gates, truck routes, unloading zones, cranes, hoists, storage and walkways are, and how deliveries are booked. It is a marked-up site drawing for each stage, with a short set of rules.

Is a construction logistics plan required?

Often, yes. In the UK it can be a planning condition. In Australia councils commonly ask for a construction management plan that covers the same ground, and most head contracts ask the builder for one. Check your permit and your contract.

Who prepares the site logistics plan?

The head contractor's site manager or project manager, with input from the crane and hoist suppliers and the main trades. It is usually drafted at tender and finished before work starts on site.

What is the difference between a logistics plan and a traffic management plan?

A traffic management plan deals with vehicles and pedestrians on public roads and at the site entry, and is usually approved by the council or road authority. The logistics plan is wider: it also covers unloading, cranes, hoists, storage and deliveries inside the site.

How often should the logistics plan be updated?

At every change of stage, such as from structure to facade, and whenever a gate, crane or hoist moves. The delivery booking schedule that goes with it is updated every day.

Put this to work on your job.

Pick the modules you need, see your price and share it with whoever signs it off. No call needed.

Read enough? See it on your job.

Start free with your own company, up to 2,000 items, or build your Matrak: pick your modules and see your price. Prefer a walkthrough? Book a demo.

Free for your own company, up to 2,000 items, no card needed · Modules for one project or every project · AI Takeoff from A$89 a trade