A snagging list template is a ready-made table for recording snags, the small defects and unfinished items found when a building is inspected before handover: where each snag is, what is wrong, which trade puts it right and when it is signed off. Ours is a free Excel file with a room-by-room snagging checklist.
Snagging is the word in the UK and Ireland. The same job is a punch list in the United States and Canada and a defects list in Australia and New Zealand.
Snag list template: the columns it needs
| Column | What goes in it |
|---|---|
| Snag no. | A number that stays with the snag until it is signed off |
| Plot and room | Plot 12, bathroom. Exact enough to walk straight to it |
| Element | Door, window, worktop, sealant, decoration |
| Snag | What is wrong, in one line |
| Trade | The one trade who puts it right |
| Raised by and date | Who found it, and when |
| Target date | When it must be put right |
| Status | Open, fixed or closed |
| Signed off | Who re-inspected it, and when |

Snagging checklist: room by room
Walk every room clockwise from the door. Look, touch and operate.
| Area | What to check |
|---|---|
| External | Brickwork and pointing, render, roof tiles, flashings, gutters, paths, drain covers, fences |
| Entrance and hall | Front door closes and locks, threshold sealed, stairs and balustrade firm |
| Walls and ceilings | Plaster flat, no cracks or nail pops, paint even with no misses or runs |
| Floors | Level, no squeaks, tiles sound and grouted, skirting fixed and sealed |
| Doors and windows | Open, close and lock, even gaps, glass unscratched, trickle vents fitted |
| Kitchen | Units level, doors aligned, worktop joints tight, appliances work |
| Bathrooms | Sanitaryware firm, no leaks, sealant neat, extractor fan runs |
| Electrics | Every socket and switch works, consumer unit labelled, smoke alarms sound |
| Heating and plumbing | Radiators heat, boiler commissioned, stopcock found, no drips |
| Loft and storage | Insulation laid evenly, loft hatch fits, shelves fixed |
One walk, nothing retyped at the desk. With Matrak Defects you pin each snag on the drawing with a photo as you walk.
Example snagging report
A snagging report is the snagging list with a cover page and photos, issued after the inspection. Five snags from one plot:
| Snag no. | Plot and room | Snag | Trade | Status |
|---|---|---|---|---|
| 1 | Plot 12, kitchen | Worktop joint open beside the sink | Kitchen fitter | Open |
| 2 | Plot 12, bathroom | Sealant missing behind the basin | Plumber | Fixed |
| 3 | Plot 12, bedroom 2 | Window handle stiff and will not lock | Window installer | Open |
| 4 | Plot 12, landing | Paint run on the balustrade | Decorator | Closed |
| 5 | Plot 12, front elevation | Pointing missed under the bay window cill | Bricklayer | Open |
Fixed means the trade says it is done. Closed means someone has re-inspected and signed it off.
When should you snag?
- Trade by trade. Each trade snags its own work before it leaves a plot. A snag costs least to fix while the trade is still on site.
- Before handover. The site manager walks the finished plot, then the client or buyer.
- After handover. Snags found later are put right in the defects period. See the defects liability period.
On a new home, most warranties give the builder two years to put snags right. Check your own warranty and contract.
Free snagging list template
Our snagging checklist template is an Excel file with three sheets: a blank snagging list, the room-by-room checklist above and a worked example. Print it on A4, or save it from Excel as a snagging checklist PDF to mark up on a tablet. It works for a house or a flat, and as a construction snag list template on a commercial fit-out.
| Snag no. | Plot and room | Element | Snag | Trade | Target date | Status |
|---|---|---|---|---|---|---|
| 1 | ||||||
| 2 | ||||||
| 3 |
Common snagging mistakes
- Snagging in poor light. Decoration snags show in daylight. Walk by day, with the lights on as well.
- 'Make good decoration'. Say which wall and what is wrong, or it comes back half done.
- No photo. A photo ends the argument about whether it was there at handover.
- Signing off from the van. A snag is closed when someone has looked at it again.
- A new list each visit. Keep one list and one set of numbers per plot.

Snagging on the drawing, with Matrak
| Matrak Defects | Paper or spreadsheet | |
|---|---|---|
| A number, a room and a trade on every snag | Yes | Yes |
| Each snag pinned on the drawing | Yes | No |
| A photo taken as you walk | Yes | No |
| The trade sees its snags on its own phone | Yes | No |
| A due date on every snag | Yes | No |
| The trade adds a photo when it is put right | Yes | No |
How Matrak does it. Walk the plot and pin each snag on the drawing with a photo. The trade gets it on their phone with a due date, puts it right and adds a photo. $7,200 for one project for a year with 50 subcontractor companies included, or $3,600 for your own company (A$, plus GST).
Why handover is a short list. Plots, rooms and trades are read from your drawings, fetched from Procore, Aconex and Autodesk, and each snag carries a full audit history of who raised, fixed and closed it.
Looking at snagging tools? See how Matrak compares, including Matrak vs PlanRadar. More on the three names for this list: punch list vs snag list vs defects list.
Frequently asked questions
What is a snagging list?
A snagging list is a record of the small defects and unfinished items in a new or refurbished building, made at an inspection before handover. Each snag has a location, a description, the trade responsible and a status.
What is the difference between a snag and a defect?
In everyday use a snag is minor: a paint run, a stiff handle, missing sealant. A defect is anything not built to the contract, and can be serious, such as a leak or a crack. Contracts usually talk about defects. Snagging is the site word for finding the minor ones before handover.
Who should do the snagging inspection?
The site manager snags every plot before handover, after each trade has checked its own work. A buyer or client can then do their own inspection, or pay an independent snagging inspector to do it.
When should snagging be done?
When the work is finished and clean, before handover. Snag too early and you list work that is simply not done yet. Snags found after handover are dealt with in the defects period.
Is a snagging list the same as a punch list?
Yes. Snagging list is the UK and Irish name, punch list is used in the United States and Canada, and defects list in Australia and New Zealand.