Snagging list template and checklist

A floor plan of Level 02 in Matrak with every apartment coloured by status, the drawing each snag on a snagging list is pinned to

A snagging list template is a ready-made table for recording snags, the small defects and unfinished items found when a building is inspected before handover: where each snag is, what is wrong, which trade puts it right and when it is signed off. Ours is a free Excel file with a room-by-room snagging checklist.

Snagging is the word in the UK and Ireland. The same job is a punch list in the United States and Canada and a defects list in Australia and New Zealand.

Snag list template: the columns it needs

ColumnWhat goes in it
Snag no.A number that stays with the snag until it is signed off
Plot and roomPlot 12, bathroom. Exact enough to walk straight to it
ElementDoor, window, worktop, sealant, decoration
SnagWhat is wrong, in one line
TradeThe one trade who puts it right
Raised by and dateWho found it, and when
Target dateWhen it must be put right
StatusOpen, fixed or closed
Signed offWho re-inspected it, and when
Matrak construction defect management software used for snagging: a list by apartment and trade with statuses being fixed, closed, overdue and ready to check, beside the phone form for one snag

Snagging checklist: room by room

Walk every room clockwise from the door. Look, touch and operate.

AreaWhat to check
ExternalBrickwork and pointing, render, roof tiles, flashings, gutters, paths, drain covers, fences
Entrance and hallFront door closes and locks, threshold sealed, stairs and balustrade firm
Walls and ceilingsPlaster flat, no cracks or nail pops, paint even with no misses or runs
FloorsLevel, no squeaks, tiles sound and grouted, skirting fixed and sealed
Doors and windowsOpen, close and lock, even gaps, glass unscratched, trickle vents fitted
KitchenUnits level, doors aligned, worktop joints tight, appliances work
BathroomsSanitaryware firm, no leaks, sealant neat, extractor fan runs
ElectricsEvery socket and switch works, consumer unit labelled, smoke alarms sound
Heating and plumbingRadiators heat, boiler commissioned, stopcock found, no drips
Loft and storageInsulation laid evenly, loft hatch fits, shelves fixed

One walk, nothing retyped at the desk. With Matrak Defects you pin each snag on the drawing with a photo as you walk.

Example snagging report

A snagging report is the snagging list with a cover page and photos, issued after the inspection. Five snags from one plot:

Snag no.Plot and roomSnagTradeStatus
1Plot 12, kitchenWorktop joint open beside the sinkKitchen fitterOpen
2Plot 12, bathroomSealant missing behind the basinPlumberFixed
3Plot 12, bedroom 2Window handle stiff and will not lockWindow installerOpen
4Plot 12, landingPaint run on the balustradeDecoratorClosed
5Plot 12, front elevationPointing missed under the bay window cillBricklayerOpen

Fixed means the trade says it is done. Closed means someone has re-inspected and signed it off.

When should you snag?

  • Trade by trade. Each trade snags its own work before it leaves a plot. A snag costs least to fix while the trade is still on site.
  • Before handover. The site manager walks the finished plot, then the client or buyer.
  • After handover. Snags found later are put right in the defects period. See the defects liability period.

On a new home, most warranties give the builder two years to put snags right. Check your own warranty and contract.

Free snagging list template

Our snagging checklist template is an Excel file with three sheets: a blank snagging list, the room-by-room checklist above and a worked example. Print it on A4, or save it from Excel as a snagging checklist PDF to mark up on a tablet. It works for a house or a flat, and as a construction snag list template on a commercial fit-out.

Snag no.Plot and roomElementSnagTradeTarget dateStatus
1
2
3

Common snagging mistakes

  • Snagging in poor light. Decoration snags show in daylight. Walk by day, with the lights on as well.
  • 'Make good decoration'. Say which wall and what is wrong, or it comes back half done.
  • No photo. A photo ends the argument about whether it was there at handover.
  • Signing off from the van. A snag is closed when someone has looked at it again.
  • A new list each visit. Keep one list and one set of numbers per plot.
A Matrak issues register of defective facade items, each with its photo: how a snag is recorded with its evidence

Snagging on the drawing, with Matrak

Matrak DefectsPaper or spreadsheet
A number, a room and a trade on every snagYesYes
Each snag pinned on the drawingYesNo
A photo taken as you walkYesNo
The trade sees its snags on its own phoneYesNo
A due date on every snagYesNo
The trade adds a photo when it is put rightYesNo

How Matrak does it. Walk the plot and pin each snag on the drawing with a photo. The trade gets it on their phone with a due date, puts it right and adds a photo. $7,200 for one project for a year with 50 subcontractor companies included, or $3,600 for your own company (A$, plus GST).

Why handover is a short list. Plots, rooms and trades are read from your drawings, fetched from Procore, Aconex and Autodesk, and each snag carries a full audit history of who raised, fixed and closed it.

Looking at snagging tools? See how Matrak compares, including Matrak vs PlanRadar. More on the three names for this list: punch list vs snag list vs defects list.

Frequently asked questions

What is a snagging list?

A snagging list is a record of the small defects and unfinished items in a new or refurbished building, made at an inspection before handover. Each snag has a location, a description, the trade responsible and a status.

What is the difference between a snag and a defect?

In everyday use a snag is minor: a paint run, a stiff handle, missing sealant. A defect is anything not built to the contract, and can be serious, such as a leak or a crack. Contracts usually talk about defects. Snagging is the site word for finding the minor ones before handover.

Who should do the snagging inspection?

The site manager snags every plot before handover, after each trade has checked its own work. A buyer or client can then do their own inspection, or pay an independent snagging inspector to do it.

When should snagging be done?

When the work is finished and clean, before handover. Snag too early and you list work that is simply not done yet. Snags found after handover are dealt with in the defects period.

Is a snagging list the same as a punch list?

Yes. Snagging list is the UK and Irish name, punch list is used in the United States and Canada, and defects list in Australia and New Zealand.

Put this to work on your job.

Pick the modules you need, see your price and share it with whoever signs it off. No call needed.

Read enough? See it on your job.

Start free with your own company, up to 2,000 items, or build your Matrak: pick your modules and see your price. Prefer a walkthrough? Book a demo.

Free for your own company, up to 2,000 items, no card needed · Modules for one project or every project · AI Takeoff from A$89 a trade