A defect report template is a set layout for recording building defects after an inspection: where each defect is, what is wrong, how serious it is, a photo, and who must fix it by when. This page has a free building defect report template for Excel, with a defect notice to send to the builder or subcontractor.
Defects is the word in Australia and New Zealand. The same record is a snagging list in the UK and a punch list in the United States and Canada.
What is in a building defects report?
- Cover details. The property or project, who inspected, the date, and why: before handover, during the defects liability period, or at the end of it.
- A summary. How many defects, by category and by trade.
- The defect list. One line for each defect.
- Photos. Numbered to match the list.
- Next steps. Who fixes what by when, and the re-inspection date.
The defect list: what to record
| Column | What to write | Example |
|---|---|---|
| Ref. | A number that never changes | D-014 |
| Location | Level, apartment and room | Level 3, Apartment 305, ensuite |
| Defect | What you can see, not what you think caused it | Water stain on the ceiling under the shower above |
| Category | Major, minor or incomplete | Major |
| Reference | The drawing, specification or standard not met | AS 3740, waterproofing specification |
| Photo | The photo number | 1 |
| Trade | Who must fix it | Waterproofing |
| Rectify by | A date, not 'as soon as possible' | Friday 20 March |
| Status | Open, fixed or closed | Open |
Major stops the space being used as intended, or will get worse: leaks, cracking, missing fire stopping. Minor is cosmetic or quick to fix. Incomplete is work not finished. Contracts and state laws define a major defect in their own words, so check yours.

How to do a defect inspection
- Take the drawings and the last list. You are checking against what was meant to be built.
- Walk the same route in every room. Clockwise from the door, floor, walls, ceiling.
- Look, touch and operate. Open every door and window, run every tap, try every switch.
- One defect, one line, one photo. With the location in the photo or its name.
- Grade as you go. Major, minor or incomplete.
- Send the defect inspection report within a day. While everyone remembers the walk.
Stop chasing defects by email. Matrak Defects puts each one on the drawing and in front of the right trade.
Example: defect report for one apartment
| Ref. | Location | Defect | Category | Trade | Status |
|---|---|---|---|---|---|
| D-014 | Apartment 305, ensuite | Water stain on the ceiling under the shower above | Major | Waterproofing | Open |
| D-015 | Apartment 305, kitchen | Stone benchtop chipped at the sink cut-out | Minor | Stonemason | Open |
| D-016 | Apartment 305, bedroom 2 | Sliding door drops off its track | Minor | Glazier | Fixed |
| D-017 | Apartment 305, living | Skirting not fitted behind the entry door | Incomplete | Carpenter | Open |
| D-018 | Apartment 305, balcony | Water ponds against the door sill after rain | Major | Tiler | Open |
The defect notice: ask in writing
The report says what is wrong. The defect notice tells the builder or subcontractor to fix it under the contract. It needs:
- The project, the contract and the date.
- The contract clause you rely on, usually the defects clause.
- The defects, by reference number, with the report and photos attached.
- The date to fix them by, and how to get access.
- What the contract allows if they are not fixed.
- A signature, and proof of when it was sent.
Send it the way the contract says notices are served. How long the builder stays responsible is covered in the defects liability period.
Free defect report template
Take our defect report template for Excel: a cover block, a defect list template with drop-downs for category and status, a one-page defect notice and a worked example. It prints on A4. No sign-up.
| Ref. | Location | Defect | Category | Trade responsible | Rectify by | Status |
|---|---|---|---|---|---|---|
| D-001 | ||||||
| D-002 | ||||||
| D-003 |
Common mistakes in defect reports
- Guessing the cause. Write what you see. 'Water stain on ceiling' is a fact. 'Failed membrane' is an argument.
- No location in the photo. Forty photos of white walls help nobody.
- One line for five defects. 'Paint defects throughout' cannot be closed.
- No date to fix by. A list with no dates is a wish list.
- A fresh report every visit. Keep one list and one set of numbers, so nothing drops off between visits.

The defects list that closes itself out
| Matrak Defects | Report in Excel or Word | |
|---|---|---|
| A reference, a location and a trade on every defect | Yes | Yes |
| Logged on the drawing where it is | Yes | No |
| A photo attached as you walk | Yes | No |
| Sent straight to the right trade | Yes | No |
| You watch each defect close | Yes | No |
| Nobody can say they missed it | Yes | No |
How Matrak does it. Log a defect on the drawing with a photo, send it to the right trade and watch it close. Every defect keeps its owner, date and photos. Matrak Defects is $7,200 for one project for a year with 50 subcontractor companies included, or $3,600 for your own company only (A$, plus GST).
Why there is no register to build. The rooms and trades come off your drawings, which Matrak fetches from Procore, Aconex and Autodesk, and every change to a defect is kept in a full audit history.
Choosing a defects system? See how Matrak compares, and read the best construction defect management software. Getting close to handover? See practical completion.
Frequently asked questions
What is a building defects report?
It is a written record of the defects found in an inspection of a building: each defect's location, description, category and photo, with who must fix it and by when. Builders use it before handover, and owners and owners corporations use it during the defects liability period.
What is the difference between a defect report and a defect notice?
The report records what is wrong. The notice is the formal request, under the contract, for the builder or subcontractor to fix the listed defects by a date. The report is usually attached to the notice.
Who can prepare a defect report?
The builder's own site team prepares one before handover. Owners, strata committees and clients often ask an independent building inspector or consultant to prepare theirs, so that it carries more weight.
What counts as a major defect?
It depends on your contract and your state's law, which each define it in their own words. In general it is a defect in a major part of the building that stops it being used as intended or threatens the structure. Get advice for your own case.
How long does a builder have to fix defects?
The contract sets a defects liability period, commonly 12 months from practical completion on commercial work, and the notice sets the date for each fix. Statutory warranties for home building are separate and differ by state. Check your contract.