A punch list template is a blank table for the items still to fix or finish at the end of a job: where each one is, what is wrong, which trade owns it, when it is due and whether it is closed. Download ours for Excel below, or copy the columns.
Punch list is the word in the United States and Canada. The same list is a snag list in the UK and Ireland and a defects list in Australia and New Zealand, and the columns do not change: see punch list vs snag list vs defects list.
Columns of a construction punch list template
| Column | What goes in it | Tip |
|---|---|---|
| No. | A number that never changes | Trades quote it when they report back |
| Location | Level, unit and room | Exact enough to walk straight to it |
| Item | What is wrong or unfinished, in one line | 'Paint touch-up, door frame, hinge side' beats 'paint' |
| Trade | The one subcontractor who owns it | One item, one owner |
| Priority | A, B or C | A before turnover, B before final payment, C agreed to leave |
| Raised and due | The date found and the date to fix by | No due date, no fix |
| Status | Open, fixed or closed | Closed only after a re-check |
| Photo | A before photo and an after photo | The after photo saves a second walk |

Punch list example: one apartment
Six items from a walk of Unit 402, the way they should read on the list.
| No. | Location | Item | Trade | Priority | Due | Status |
|---|---|---|---|---|---|---|
| 1 | Unit 402, kitchen | Cabinet door under the sink hangs out of line | Cabinets | A | 14 Mar | Closed |
| 2 | Unit 402, bathroom | Sealant missing where the tub meets the tile | Tile | A | 14 Mar | Open |
| 3 | Unit 402, living room | Paint touch-up at the window return | Painter | B | 17 Mar | Fixed |
| 4 | Unit 402, bedroom 1 | Door rubs on the frame and will not latch | Carpenter | A | 14 Mar | Open |
| 5 | Unit 402, entry | Light switch plate cracked | Electrician | B | 17 Mar | Open |
| 6 | Level 4 corridor | Ceiling tile stained by a leak that has been repaired | Ceilings | B | 17 Mar | Open |
A fix before turnover. B fix before final payment. C agreed to leave.
Common punch list items by trade
- Paint. Touch-ups, missed coats, overspray on hardware.
- Doors and hardware. Rubbing, not latching, missing stops and keys.
- Tile and flooring. Chips, uneven edges, missing grout or sealant.
- Cabinets and counters. Doors out of line, scratches, loose handles.
- Electrical. Missing cover plates, dead outlets, unlabelled panels.
- Plumbing and HVAC. Drips, loose fixtures, missing grilles.
- Cleaning and protection. Stickers, dust, protection left on.
Handover is a short list, not a month of chasing. With Matrak Defects each item is pinned on the drawing and sent to the trade's phone.
How to run a punch list walk
- Agree when. Walk once the trade says the area is complete, before substantial completion is certified.
- Walk the same way every time. Clockwise from the door, floor to ceiling, room by room.
- One item, one line, one photo. Never 'various paint defects'.
- Send it the same day. Each trade gets only its own items, with due dates.
- Re-check and close. The trade marks an item fixed. Only the person who raised it closes it.
Items found after turnover are fixed under the warranty or defects period: see the defects liability period.
Free construction punch list template (Excel)
This free punch list template is an Excel file with the columns above, drop-downs for priority and status, and the example on a second sheet. It prints one page wide, so it also works as a paper punch list form on a clipboard.
| No. | Location | Item | Trade | Priority | Due | Status |
|---|---|---|---|---|---|---|
| 1 | ||||||
| 2 | ||||||
| 3 |
Common mistakes with punch lists
- Starting too early. A list written while trades are still working is a to-do list. Wait until they say done.
- Vague items. 'Fix door' sends a carpenter to look for a problem. Say which door and what is wrong.
- One list emailed to everyone. Forty trades scroll past 300 items that are not theirs.
- No re-check. 'Fixed' is the trade's opinion. 'Closed' is yours.
- A new list every walk. Keep one list and one set of numbers from first walk to final payment.

Your punch list, on the drawing
| Matrak Defects | Spreadsheet | |
|---|---|---|
| A number, a location and a trade on every item | Yes | Yes |
| Pinned on the drawing with a photo | Yes | No |
| Sent to the trade's phone with a due date | Yes | No |
| The trade closes it out with an after photo | Yes | No |
| Rooms and trades come off your drawings | Yes | No |
| Every item keeps its owner, date and photos | Yes | No |
How Matrak does it. Walk the unit and pin each item on the drawing with a photo. The trade gets it on their phone with a due date, fixes it and adds a photo. Matrak Defects is $7,200 for one project for a year with 50 subcontractor companies included, or $3,600 for your own company alone (A$, plus GST).
Why nothing is retyped at the desk. The rooms and trades are read from drawings fetched from Procore, Aconex and Autodesk, and each item's full audit history shows who raised it, who fixed it and who closed it.
Shopping for a punch list tool? See how Matrak compares, including Matrak vs Fieldwire. For the UK version of this list, see the snagging list template.
Frequently asked questions
What is a punch list in construction?
A punch list is the list of small items still to fix or finish near the end of a project, such as paint touch-ups, a door that will not latch or a missing cover plate. Each item has a location, an owner and a due date, and the job is not finished until the list is closed.
Who creates the punch list?
The general contractor usually walks the job first and lists items for each subcontractor. The owner and the architect then walk it and add their own before substantial completion is certified.
When is the punch list done?
At or just before substantial completion, when the work is complete enough to use. Items are then fixed before final completion and final payment.
What is the difference between a punch list and a snag list?
Only the name. Punch list is used in the United States and Canada, snag list in the UK and Ireland, and defects list in Australia and New Zealand.
What should a punch list include?
A number, the exact location, a one-line description, the trade responsible, a priority, the date raised, a due date, a status and a photo for every item.