A punch list, a snag list and a defects list are the same thing: a list of items of work that are incomplete, damaged or not built to the contract, which the contractor must fix before or just after handover. Americans say punch list, the UK and Ireland say snag list or snagging list, and Australia and New Zealand say defects list. The job, the columns and the headaches are identical.
| Term | Where it is used | Related words |
|---|---|---|
| Punch list | United States, Canada | Punch walk, punch out, punch list item |
| Snag list or snagging list | United Kingdom, Ireland | Snagging, snagging survey, de-snagging |
| Defects list | Australia, New Zealand | Defecting, defects inspection, defects liability period |
What goes on a defects list?
- Incomplete work. A missing door stop, an unpainted return, a cover plate not fitted.
- Damage. A scratched benchtop, a chipped tile, a dented door frame.
- Poor workmanship. Uneven grout, a door that binds, visible joints in plasterboard.
- Things that do not work. A power point with no power, a tap that drips, an exhaust fan not running.
- Not as specified. The wrong fitting or colour installed.
Serious problems that break a stated requirement and need a decision from the engineer or designer do not belong on the defects list. They get a non-conformance report.
Defects list template
| No. | Location | Defect | Trade | Priority | Raised | Due | Status | Evidence |
|---|---|---|---|---|---|---|---|---|
| D-101 | Unit 3.07, ensuite | Silicone missing at shower screen base | Shower screens | Before handover | 18 Nov | 25 Nov | Open | Photo |
| D-102 | Unit 3.07, kitchen | Chip in stone benchtop near sink | Joinery | Before handover | 18 Nov | 25 Nov | Fixed, to be checked | Photo |
| D-103 | Level 3 corridor, grid C4 | Paint touch-up at fire door frame | Painter | Before handover | 18 Nov | 22 Nov | Closed | Before and after photo |
| D-104 | Unit 3.08, bedroom 1 | Power point not working | Electrician | Urgent | 18 Nov | 19 Nov | Open | Photo |
Each item needs exactly one location, one trade and one status. An item like 'various paint defects, level 3' cannot be assigned, fixed or closed.
Tired of typing up the walk-through afterwards? With Matrak Defects you log each defect on the drawing from your phone, it goes straight to the right trade, and overdue ones are chased for you.
When is the defects list made?
- During the job. Good teams log defects as each trade finishes an area, not in one walk at the end.
- Before practical completion. A full inspection of every room, first by the head contractor, then with the client or superintendent. See practical completion.
- At handover. The agreed list of minor items still open, with dates.
- During the defects liability period. New items reported by the owner or occupants. See the defects liability period.
How do you run a defects list on the drawing?
A defect is a place before it is anything else. Pinning each one to the floor plan fixes most of what goes wrong with spreadsheet lists:
- No arguments about where. The pin shows the exact wall or fitting, with a photo.
- Trades see only their own. The painter opens the plan and sees the painter's pins, level by level.
- Walk order. Fixing and re-inspecting follow the plan, not the order items were typed.
- Patterns show up. Twenty pins on the same detail in every unit is a method problem, not twenty defects.
- Status at a glance. Open, fixed and closed pins by level show whether handover is on track.
The process itself is simple. Find it, pin it with a photo, assign it to one trade with a date, the trade fixes it and adds a photo, the inspector checks and closes it. Only the inspector closes.
What are the common mistakes with defects lists?
- One big walk at the end. Thousands of items land at once, when the trades have already left site.
- Vague items. No exact location, no photo, more than one trade on one line.
- Trades closing their own items. Fixed is not closed until someone else has looked.
- Several lists. The builder's spreadsheet, the client's PDF and the architect's email. Merge them into one.
- No dates. An item without a due date never becomes overdue, so it never gets chased.
- Losing the history. At the end of the defects liability period you need to show when each item was reported, fixed and closed.
Comparing tools? Read the best construction defect management software or see how products compare on the compare hub.
Defects lists in Matrak
How Matrak does it. With Matrak's Defects module you log a defect on the drawing, send it to the right trade and watch it close. On the phone app you open the drawing, tap the room or item, choose Report defect, add photos and save. The defect is linked to that spot, the trade is told, and overdue items are chased by email and in the app. Every change is kept, with who did it and when. Defects for a team is $7,200 for one project for a year with 50 subcontractor companies included, or $3,600 for your own company only (A$, plus GST). Defects is in early access: you can price it and add it today.
Why the trades use it. Your own staff are free and 50 subcontractor companies come with the module, so every trade works from its own list on its own phone. The defect sits on the same drawings as the ITPs, the progress and the products that were installed. Matrak integrates with Procore, Aconex and Autodesk, so the drawings are fetched with nothing to download and new revisions are picked up as they land. Every change is kept in a full audit history, whether a person or the AI made it.
Frequently asked questions
Is a punch list the same as a snag list?
Yes. Punch list is the North American term and snag list is the British and Irish term for the same list of incomplete or defective items to fix around handover. In Australia it is called a defects list.
Punch list meaning: why is it called that?
The usual explanation is that a hole was once punched in the paper list beside each item as it was completed. The name stuck in North America.
Who prepares the defects list?
The head contractor prepares its own list first, then inspects with the client, architect or superintendent, who add theirs. The head contractor assigns each item to the subcontractor responsible.
What is the difference between a defect and a non-conformance?
A defect is fixed by the trade to the original requirement without anyone's permission. A non-conformance needs a formal decision about whether the work can stay, be repaired or must be redone, and a record of the cause.
How many defects are normal at handover?
It varies a great deal with the size and type of building and how well checks were done during the job. The aim is a short list of minor items at practical completion, which comes from inspecting early and by area.
What is a punch list in construction?
The usual punch list definition on a North American job: the list of items the contractor must complete or correct before final payment, written up around substantial completion.
What is snagging in construction?
Snagging is the UK and Irish word for inspecting finished work and listing what is incomplete or defective. The snagging meaning is the same as punching out a job in North America or defecting in Australia. A snagging inspection is the walk-through that produces the snag list, and snagging management is assigning, fixing and closing each snag.