Build my Matrak
Supply chain

Non-conformance report (NCR) in construction: what it is, with a template

A non-conformance report (NCR) is a formal record that work, material or a process did not meet a stated requirement: the drawings, the specification, a standard or the approved method. It says what is wrong, why it happened, how it will be fixed, and what will stop it happening again. An NCR stays open until the fix is checked and signed off.

NCRs come from quality management systems built on ISO 9001, which asks an organisation to control work that does not meet requirements and to act on the cause. On site, an NCR is the paper trail for a problem too serious for a quick fix-and-move-on.

When do you raise an NCR (non-conformance report)?

  • A hold point was missed and the work was covered up.
  • A test failed: concrete cylinders under strength, a flood test that leaked, a weld that failed inspection.
  • The wrong material or product was installed, or a substitute was used without approval.
  • Work was built to a superseded drawing revision.
  • The same defect keeps coming back, which points to a problem with the method, not one tradesperson.
  • The fix needs a decision from the designer or engineer (use as is, repair, or pull out and redo).

NCR vs defect vs RFI: what is the difference?

NCRDefectRFI
What it isWork or process that broke a stated requirement and needs a formal decisionA fault in finished work to be fixed to the original requirementA question to the design team before the work is built
ExampleSlab poured without the engineer's reinforcement inspectionChipped tile, door that does not latchDrawing and spec disagree on the membrane type
Needs a cause and prevention step?YesNot usuallyNo
Who decides the fixHead contractor, often with the engineer or designerThe trade fixes it, the inspector closes itThe designer answers
How commonRare, and each one mattersVery common, most are minorCommon during construction

A simple test: if the trade can fix it to the drawing with no one's permission, it is a defect. If someone has to decide whether the work can stay, it is an NCR. For running the day-to-day list see punch list vs snag list vs defects list.

Tracking NCRs, defects and ITPs in three places? Matrak Quality and Defects keep them on the drawing, against the room or item they belong to, with every trade working from the same record.

Non-conformance report template: the fields to fill

Copy this template. One NCR per issue.

FieldWhat to writeExample
NCR number and dateA unique number and the date raisedNCR-023, 18 Nov 2026
Raised by / issued toWho found it and which company must respondSite engineer to the formwork subcontractor
Location and lotLevel, grid, room or pour, and the ITP line if there is oneLevel 4, pour 4B, ITP line 3
Requirement not metThe drawing, spec clause or standardS-204 rev C, cover 40 mm to bottom bars
DescriptionWhat was found, with photos and measurementsCover measured at 20 to 25 mm over about 6 m2
Immediate actionWhat was done to contain itArea marked, pour stopped
Root causeWhy it happenedWrong chairs delivered, not checked before fixing
DispositionUse as is, repair, rework, or reject, and who approved itRework: re-chair and re-inspect. Approved by the structural engineer
Corrective actionThe change that stops a repeatChair height added to the pre-pour checklist
Verification and close-outWho checked the fix, date, evidenceEngineer's re-inspection passed, photos attached, closed 20 Nov 2026

How do you close out an NCR?

  1. Raise it straight away and stop the affected work so the problem does not get built in.
  2. Record the evidence before anything is touched: photos, measurements, test results, the drawing revision.
  3. Issue it to the responsible company with a date to respond.
  4. Agree the disposition. The subcontractor proposes the fix. The head contractor, and the engineer or designer where needed, approve it in writing.
  5. Do the fix and re-inspect against the original requirement or the approved concession.
  6. Record the corrective action that prevents a repeat, and check it was actually put in place.
  7. Close it with a name, a date and the evidence, and keep it for the handover pack.

What are the common mistakes with NCRs?

  • Using NCRs as punishment. If an NCR means a back-charge every time, people stop reporting problems. Keep the report about the work.
  • Raising an NCR for every scratch. Minor faults belong on the defects list. Too many NCRs bury the serious ones.
  • Closing without a cause. 'Fixed' is a correction. A corrective action changes the method so it does not happen on the next level.
  • No sign-off from the designer when the fix departs from the drawings. A use-as-is decision needs their approval in writing.
  • NCRs left open at practical completion. Open NCRs can hold up the certificate and the final payment.

Related guides: what an ITP is in construction, quality assurance vs quality control and the best construction defect management software.

Raising and closing NCRs in Matrak

How Matrak does it. In Matrak a failed check moves its ITP to Issues by itself, so nothing that failed can sit quietly as 'in progress'. From the phone app you open the drawing, tap the item or room, report the problem with photos, and it is linked to that record and sent to the right trade to close. Every change is kept, with who did it and when. Quality is $18,000 for one project for a year with 50 subcontractor companies included. Defects for a team is $7,200 for one project for a year, or $3,600 for your own company only (A$, plus GST).

Why it is less work. The set-up is done for you from the drawings, and they are the same drawings that drive AI takeoff, supply chain and progress, so nothing is keyed in twice. Matrak integrates with Procore, Aconex and Autodesk, so the drawings are fetched with nothing to download and new revisions are picked up as they land. Your own staff are free. Every change is kept in a full audit history, whether a person or the AI made it.

Frequently asked questions

What does NCR stand for in construction?

NCR stands for non-conformance report. It records work, material or a process that did not meet a stated requirement, the agreed fix, and the action taken to stop it happening again.

Who can raise an NCR?

Anyone responsible for quality on the project: the head contractor's site or quality team, the subcontractor's own supervisor, or the client's representative. Subcontractors raising NCRs on their own work is a sign of a healthy system.

What is the difference between a correction and a corrective action?

A correction fixes the problem in front of you, such as re-fixing the reinforcement. A corrective action removes the cause, such as adding a chair-height check to the pre-pour checklist.

Does an NCR mean a back-charge?

Not by itself. The NCR records the problem and the fix. Who pays is decided under the contract or subcontract.

How long should an NCR stay open?

Only as long as the fix takes. Set a response date when you issue it, and review open NCRs weekly. Old open NCRs usually mean nobody owns the decision.

Sources

  • ISO 9001 (quality management systems) is the standard most construction quality systems follow for control of nonconforming work and corrective action. Check the edition your company is certified to.
  • Matrak: quality tracking in Matrak

Last reviewed 18 November 2026. This guide is general information for people working in construction. It is not legal or contract advice. Check your own contract and the current legislation, or ask a construction lawyer, before you rely on it.

Put this to work on your job.

Pick the modules you need, see your price and share it with whoever signs it off. No call needed.

Read enough? See it on your job.

Start free with your own company, up to 2,000 items, or build your Matrak: pick your modules and see your price. Prefer a walkthrough? Book a demo.

Free for your own company, up to 2,000 items, no card needed · Modules for one project or every project · AI Takeoff from A$89 a trade