A construction estimate template is a spreadsheet that prices a job one item at a time: each item of work with a quantity, a unit and a rate, added up, then preliminaries, overheads, margin and tax on top. Ours is free to download below, with the totals already working.
Estimators in Australia, New Zealand and the UK call the measured list a bill of quantities and the cost of running the site preliminaries. In the US and Canada the same things are the takeoff and general conditions. The sums are identical.
What goes in a construction estimate
- Quantities. Areas, lengths and counts measured off the current drawings. See quantity takeoff.
- Rates. Material, labour and plant for one unit of each item.
- Quotes. Subcontractor and supplier prices, as their own lines.
- Preliminaries. Supervision, scaffold, hoists, sheds, insurance.
- Overheads and margin. Head office costs, then profit.
- Contingency. An allowance for what the drawings do not show yet.
- Exclusions and assumptions. What the price leaves out. This is the page you point to when scope is argued.
- Tax. GST in Australia, New Zealand and Canada, VAT in the UK, sales tax where it applies in the US.

Three kinds of estimate
| Estimate | Built from | Use it for |
|---|---|---|
| Order of magnitude | A rate per square metre from past jobs | Deciding whether to chase the project |
| Elemental or budget | A rate for each element: structure, facade, services, fit-out | Setting a budget while the design is moving |
| Detailed | Every item measured off the drawings and priced | Tenders, quotes and any price you will be held to |
This template is for the third kind.
Tender due and nobody free to measure it? Matrak Estimating measures the job from your drawings and prices it from your own lists. One AI takeoff is $89 a trade, and it can save over $2,000 of estimating labour on one project.
How to fill in the estimate template
- Write down the drawings you are pricing, with their revision letters.
- Measure the quantities, one line per item, with the unit.
- Put a rate on each line. Allow for waste in the quantity or in the rate, never both.
- Add subcontractor and supplier quotes as their own lines.
- Add preliminaries, overheads, margin and contingency.
- List the exclusions and assumptions.
- Have a second person check the five biggest lines before it goes out.
Worked example: partitions for one office floor
Internal partitions and doors for one floor of an office fit-out. The rates are made up for the example: use your own.
| Item | Description | Qty | Unit | Rate | Total |
|---|---|---|---|---|---|
| 1 | Steel stud wall framing, 92 mm | 180 | m2 | $60 | $10,800 |
| 2 | 13 mm plasterboard, both sides, set | 360 | m2 | $30 | $10,800 |
| 3 | Acoustic insulation batts | 180 | m2 | $15 | $2,700 |
| 4 | Solid core door, frame and hardware, hung | 12 | no | $800 | $9,600 |
| 5 | Skirting, painted | 240 | m | $15 | $3,600 |
| Direct cost | $37,500 | ||||
| Preliminaries, 8% of direct cost | $3,000 | ||||
| Overheads, 10% | $4,050 | ||||
| Margin, 10% | $4,455 | ||||
| Contingency, 2% of direct cost | $750 | ||||
| Price, excluding GST | $49,755 |
The mark-ups add about a third to the direct cost. Leave one out and the job is priced at a loss before it starts.
Free construction estimate template for Excel
Take our construction estimate template for Excel: these columns with working formulas on a sheet that prints on A4, plus the partitions example filled in. No sign-up.
| Item | Description | Qty | Unit | Material rate | Labour rate | Plant rate | Rate | Total |
|---|---|---|---|---|---|---|---|---|
| 1 | Steel stud wall framing, 92 mm | 180 | m2 | $28 | $32 | $0 | $60 | $10,800 |
| 2 | 13 mm plasterboard, both sides, set | 360 | m2 | $9 | $21 | $0 | $30 | $10,800 |
A template still needs every quantity measured by hand. Once the price is accepted, a change to the scope is a change order.
Common mistakes in a construction estimate
- Pricing an old revision. Write the revision on the estimate and re-measure when a new one lands.
- Counting an item twice. The door on the plan and the door on the schedule are one door.
- Mixed units. Lineal metres priced at a square metre rate.
- No waste. Laps, offcuts and breakages are real quantities.
- Preliminaries left out. The site still has to be run.
- A total typed over a formula. The sheet stops adding up and nobody notices.
- No exclusions. Then everything is included.
Estimate template or estimating software?
| Spreadsheet template | Matrak | |
|---|---|---|
| Quantities | Measured by hand, sheet by sheet | Measured by AI from the whole drawing set, checked by a person |
| Rates | Typed in, or copied from the last job | From your own product and price lists |
| Proof | A number in a cell | Every quantity marked on the drawing it came from |
| Output | The spreadsheet | A priced bill and a quote in your own Excel format |
How Matrak does it. Matrak Estimating starts at the drawings: AI Takeoff measures over 1,000 documents in one pass, each item counted once across plans, elevations and schedules. Lines are priced from your own price lists and the quote comes back in your Excel format. $89 a trade, or from $65 a credit on a plan (A$, plus GST).
Why it pays for itself. Measuring one project by hand can cost over $2,000 of an estimator's time. Drawings are fetched from Procore, Aconex and Autodesk with nothing to download, the library covers over 90 trades, and every change is kept in a full audit history, whether the AI or a person made it.

Comparing tools? See the best construction estimating software in Australia or how Matrak compares.
Frequently asked questions
What is a construction estimate template?
It is a spreadsheet laid out to price a building job: one line for each item of work with its quantity, unit and rate, a total for each line, and the mark-ups for preliminaries, overheads, margin and tax underneath.
What should a construction estimate include?
Measured quantities, a rate for each item, subcontractor and supplier quotes, preliminaries, overheads, margin, a contingency, tax, and a list of exclusions and assumptions. Note the drawing numbers and revisions the price is based on.
What is the difference between an estimate and a quote?
An estimate is your working-out of what the job should cost. A quote is the price you offer the customer, and once it is accepted you are usually held to it. The quote is built from the estimate, with the exclusions written on it.
How much contingency should a construction estimate allow?
It depends on how finished the drawings are. Allow more at concept stage and less as the design is completed, often only a few per cent on fully documented work. Price a known risk as its own line instead of hiding it in contingency.
Can I use Excel for construction estimating?
Yes. Excel suits small jobs and one-off prices, and this template gives you the layout and the formulas. It gets slow when the drawings keep changing, because every quantity has to be measured and typed again by hand.