Change order template for construction

What a change order is built from: a Matrak variation report comparing revision C and revision D quantities with the value added and removed, beside the phone record for one variation

A change order template is a one-page form that records a change to a construction contract: what is changing, why, what it adds to or takes off the price, how many days it adds, and who has signed. Download ours below, free: a change order form and a change order log in one Excel file.

Change order is the US and Canadian term. In Australia, New Zealand and the UK the same document is a variation: see construction variations for that process.

What is a change order in construction?

A construction change order is a written, signed amendment to the contract. The contract fixes a scope, a price and a finish date. A change order moves one or more of them, and once both sides sign, it is part of the contract.

It usually starts as a change order request: the contractor prices the change and submits it. It becomes a change order when the owner approves it. Where the owner wants work to start before the price is agreed, many contracts use a separate written direction, such as a construction change directive under AIA contracts in the US.

Where most change orders start: a Matrak list of drawing sheets with their old and new revision and the number of changes found, beside one revision overlaid on the last

What a change order form must say

  • A number and a date. Numbered in order, never reused.
  • What is changing. Clear enough for a stranger to price, with the drawing, RFI or instruction it came from.
  • Why. Owner request, design change, site condition, error or omission, authority requirement.
  • The cost, worked out. Labour, materials, plant and subcontractors as separate lines, then the overhead and profit the contract allows.
  • The time. Days added to the programme, or none. Say it either way.
  • The new contract sum. Original sum, changes approved so far, this change, revised total.
  • Signatures. The people the contract names, before the work starts.

Know what a change costs before the argument starts. Matrak Variations re-measures each new drawing revision against the last one and shows what changed.

Worked example: a construction change order

A tenant asks for six more power and data points in the meeting rooms after the walls are lined.

TypeDescriptionQtyUnitRateAmount
LabourElectrician, install and test14hr$95.00$1,330.00
MaterialsDouble power outlet6no$48.00$288.00
MaterialsData point, Cat 66no$85.00$510.00
MaterialsCable and conduit90m$6.50$585.00
SubcontractorPatch and paint walls after chasing1item$450.00$450.00
Subtotal$3,163.00
Overhead and profit, 10%$316.30
Total for this change$3,479.30

Original contract sum $480,000. Revised contract sum $483,479.30. One day added. Signed by the tenant's representative before a wall was chased.

Free change order template

Take our construction change order template for Excel. It has the construction change order form with the sums already working, the example above filled in, and a construction change order log that totals what is submitted, approved and still waiting. No sign-up. The log:

CO noDescriptionReasonSubmittedApprovedDaysStatus
CO-001Six power and data points, Level 2Client request$3,479.30$3,479.301Approved
CO-002Rock in the lift pit excavationSite condition$9,170.70$9,170.703Approved
CO-003Lobby floor upgraded from tile to stoneClient request$14,200.002Submitted

An approved change order is billed on the next pay application, as its own line. In Australia it goes on the progress claim.

Common mistakes with change orders in construction

  • Starting on a handshake. Work done before the signature is the hardest money to recover.
  • Missing the notice period. Most contracts give a set number of days to give notice of a change. Late notice can lose the claim.
  • A lump sum with no breakdown. It invites a dispute. Show the quantities and the rates.
  • Forgetting the time. A change that costs nothing can still add days.
  • Not spotting the change. A revised drawing with no cloud around the change gets built and never claimed.
  • No log. Without one, nobody knows the real contract sum.

Spreadsheet or change order software?

How Matrak does it. Most change orders begin with a new drawing revision. Matrak Variations re-measures the revised set against the last one and lists every line that moved: the old quantity, the new one and the difference in dollars. You walk in with the number and the marked-up drawings. $750 a month, with 10 re-measures included (A$, plus GST).

Why nothing goes unclaimed. The revised drawings are fetched from Procore, Aconex and Autodesk, so there is nothing to download. A change that shows on the plan, the elevation and the schedule is counted once, and each one is kept in a full audit history.

Pricing a change order from measured quantities: a Matrak estimate with quantity, rate and total on each line, beside the marked-up drawing the quantities came from

Weighing up tools? See how Matrak compares.

Frequently asked questions

What is a change order?

A change order is a signed written amendment to a construction contract that changes the scope of work, the contract price, the completion date, or all three.

Who prepares a change order?

Usually the contractor prices the change and submits it as a change order request. The architect or contract administrator reviews it and the owner approves it. Under some contracts the architect prepares the final change order for everyone to sign.

Is a change order the same as a variation?

Yes. Change order is the term in the US and Canada. Variation is the term in Australia, New Zealand and the UK. Both are a formal, agreed change to the contract.

What is the difference between a change order and a change directive?

A change order is agreed and signed by both sides, with the price and the time settled. A change directive is an instruction from the owner to go ahead with a change before the price or time is agreed. The cost is settled afterwards under the contract's rules.

Can a contractor refuse a change order?

It depends on the contract. Most let the owner direct changes within the general scope of the work, with the contractor entitled to be paid for them. A change outside that scope, or a price the contractor does not accept, goes through the contract's dispute process. Get advice before refusing.

What should a change order log track?

Each change order's number, date, description, reason, amount submitted, amount approved, days, status and approval date, with running totals so the revised contract sum is always known.

Put this to work on your job.

Pick the modules you need, see your price and share it with whoever signs it off. No call needed.

Read enough? See it on your job.

Start free with your own company, up to 2,000 items, or build your Matrak: pick your modules and see your price. Prefer a walkthrough? Book a demo.

Free for your own company, up to 2,000 items, no card needed · Modules for one project or every project · AI Takeoff from A$89 a trade