Schedule of values template

A schedule of values checked against the site: Matrak comparing the percentage claimed with the percentage done on site, trade by trade, and flagging amounts to query

A schedule of values template is a spreadsheet that splits a construction contract sum into lines of work, each with a dollar value, so progress is billed against each line. It sits behind every pay application. Download ours below, free, with the formulas working.

Schedule of values and pay application are US and Canadian terms. In Australia the same job is done by a progress claim with a trade breakdown, and in the UK by an application for payment.

What is a schedule of values?

A construction schedule of values (SOV) lists every part of the work and the share of the contract sum given to it. The lines add up to the contract sum exactly. It is agreed with the owner or architect before the first bill and only changes when a change order changes it. Each month you fill in how much of each line is done, and that works out what you are owed.

The columns, one by one

ColumnWhat goes in it
Item no and descriptionOne line per part of the work: by trade, area or cost code
Scheduled valueThe share of the contract sum for that line
From previous applicationsWork billed on that line in earlier periods
This periodWork done on that line since the last application
Materials presently storedMaterials bought and stored, on or off site, not yet built in
Total completed and storedThe three columns before it, added together
% completeTotal completed and stored, divided by the scheduled value
Balance to finishScheduled value, less total completed and stored
RetainageThe share of the total the owner holds back until the end
Percent complete read from the site instead of guessed: the Matrak progress tracker showing each level's status across every trade stage, from not started to in progress

How a pay application uses it

A construction pay application is a summary page with the schedule of values behind it. The summary takes the schedule's totals and works down to the cheque:

  1. Contract sum to date: the original sum plus approved change orders.
  2. Total completed and stored to date.
  3. Less retainage.
  4. Less previous payments.
  5. Current payment due.

On many US projects the forms are AIA documents G702 (the application) and G703 (the continuation sheet, which is the schedule of values). If your contract calls for an AIA pay application, use the licensed AIA forms. Our template follows the same logic for jobs where you may use your own.

Stop paying for work that is not done yet. Matrak Claims checks every line claimed against the drawings and what is done on site.

Worked example: application 3 on a fit-out

A $300,000 office fit-out, six lines, 10% retainage.

ItemDescriptionScheduled valuePreviousThis periodStoredTotal to date%Balance
1General conditions$40,000$16,000$8,000$0$24,00060%$16,000
2Demolition$25,000$25,000$0$0$25,000100%$0
3Framing and drywall$90,000$36,000$27,000$4,500$67,50075%$22,500
4Electrical$70,000$14,000$21,000$0$35,00050%$35,000
5Flooring$45,000$0$0$9,000$9,00020%$36,000
6Painting$30,000$0$3,000$0$3,00010%$27,000
Total$300,000$91,000$59,000$13,500$163,50055%$136,500

Free schedule of values template

Take our schedule of values template for Excel. It doubles as a pay application template: fill in the schedule and the summary page works out the payment due. The example is included. No sign-up. The summary for the job above:

LineAmount
Total completed and stored to date$163,500
Less retainage at 10%$16,350
Less previous payments$81,900
Current payment due$65,250

Common mistakes that delay payment

  • Lines that do not add up to the contract sum. The first thing a reviewer checks.
  • Too few lines. "Electrical, $70,000" cannot be checked. Split it by level or stage.
  • Front-loading. Early lines stuffed with value get the schedule sent back.
  • A percentage the site does not show. The reviewer walks the job.
  • Change orders buried in original lines. Add each approved change as its own line.
  • Stored materials with no proof. Attach invoices and photos, and insurance where the contract asks.
  • The wrong retainage. Check the rate and whether it drops at 50% complete.

Software that checks a pay application

How Matrak does it. Matrak Claims puts the percentage claimed beside the percentage done on site, for every trade. Quantities measured off the drawings set what 100% is, so a line claimed at 55% against 41% installed stands out with its dollar value. $400 a month, with 8 AI credits included (A$, plus GST).

Why the review is short. Both sides look at the same drawing and the same count of what is installed. Drawings come from Procore, Aconex and Autodesk with nothing to download, and a full audit history records who changed what.

What is ready to bill: a Matrak installation report counting facade panels, pods, windows and joinery from delivered and hoisted to installed, checked and claimed, beside the phone record with an install photo

Looking at pay application software? See Matrak beside Payapps, or every comparison. Retainage is usually released at practical completion, called substantial completion in North America.

Frequently asked questions

What is a schedule of values in construction?

It is a list that breaks the contract sum into lines of work, each with a dollar value. It is agreed at the start of the job and used every billing period to work out how much of the contract has been earned.

Who prepares the schedule of values?

The contractor prepares it and submits it before the first pay application. The owner, architect or lender reviews and accepts it. Subcontractors prepare their own for their subcontract.

How detailed should a schedule of values be?

Detailed enough that someone walking the site can check each line. Split big trades by level, area or stage, and keep general conditions, mobilisation and closeout as their own lines.

What is the difference between a schedule of values and a pay application?

The schedule of values is the breakdown of the contract sum. The pay application is the request for payment that uses it: a summary of what is earned, retained and already paid, with the updated schedule attached.

What is retainage on a pay application?

Retainage is a share of each payment, often 5% to 10%, that the owner holds until the work is substantially complete. It is called retention in Australia, New Zealand and the UK. Many US states cap it by law, so check your contract and your state's rules.

Do I need the AIA pay application forms?

Only if the contract asks for them. Where the contract names the AIA forms, use the licensed AIA documents. Where it only asks for an application with a schedule of values, a spreadsheet with the same columns is commonly accepted.

Put this to work on your job.

Pick the modules you need, see your price and share it with whoever signs it off. No call needed.

Read enough? See it on your job.

Start free with your own company, up to 2,000 items, or build your Matrak: pick your modules and see your price. Prefer a walkthrough? Book a demo.

Free for your own company, up to 2,000 items, no card needed · Modules for one project or every project · AI Takeoff from A$89 a trade