A site inspection checklist is a list of the things to look at on a walk of the job, each answered pass, fail or not applicable, with a note and a photo where something is wrong. A construction site inspection checklist turns 'have a look around' into the same check every time, whoever does the walk.
This one covers the work itself: is it built to the drawings, protected, and ready for the next trade. Below are the lines for a weekly walk, a waterproofing inspection checklist filled in, and a template to download.
What goes on a construction site inspection checklist?
Every line needs the same five things:
- One thing to look at. Written so the answer is yes or no.
- The standard. A drawing, a specification clause or a tolerance. 'Looks fine' is not a standard.
- A result. Pass, fail or N/A. Nothing in between.
- Evidence. A photo taken at the work, with its location.
- An action. For every fail: who fixes it, and by when.

Site inspection checklist for the weekly walk
Ten lines that suit most building sites. Add your own for the trades on the job.
| Area | What to check | Pass looks like |
|---|---|---|
| Drawings on site | Trades are working from the current revision | The revision at the work matches the register |
| Set-out | Grids, levels and openings match the drawings | Checked dimensions are within tolerance |
| Work in progress | Each trade's work matches the approved sample | No visible departure from the sample |
| Before cover-up | Work about to be covered is inspected and photographed | Hold points are released in writing |
| Penetrations and services | Sealed and tested before the linings close | Test records are on file |
| Materials | The approved product, stored dry and off the ground | Dockets match the approved product |
| Protection | Finished work is protected from the trades that follow | Floors, glass and joinery are covered |
| Housekeeping | The area is clean and clear for the next trade | No waste or stored material in the way |
| Open items | Fails from the last walk are closed or have a date | Nothing older than the agreed time |
| Records | This week's ITPs and checklists are signed | No unsigned checks for finished work |
When should you inspect?
- Before a trade starts. Is the area ready, and has the work before been accepted?
- At the first-off. The first room or panel sets the standard for the rest.
- Before cover-up. Once the ceiling closes or the tiles go down, you are checking photos, not work.
- Every week. The walk above, same route, same day.
The checklist for every room, written for you. Matrak Quality builds the checks from your drawings and puts them on the trade's phone.
Example: a waterproofing inspection checklist
One bathroom, filled in. Results are words, so the sheet reads the same in black and white.
| No. | Check | Result | Note |
|---|---|---|---|
| 1 | Substrate clean, dry and primed | Pass | Photo 1 |
| 2 | Floor falls to the waste as drawn | Pass | Checked with a level |
| 3 | Bond breaker at every wall and floor junction | Fail | Missing behind the door frame. Fixed the same day, photo 3 |
| 4 | Membrane coats and coverage to the data sheet | Pass | Two coats, batch number recorded |
| 5 | Upturns and shower extents as drawn | Pass | |
| 6 | Flood test held for the specified period, no leaks below | Pass | Photo 5 |
A fail that is found, fixed and recorded is the checklist working. For hold points and who signs each line, see ITP in construction.
Free construction checklist template
Take our inspection checklist template for Excel: the weekly walk on one sheet with a pass, fail or N/A drop-down, and the waterproofing example on a second. It prints on A4. No sign-up.
| No. | Area | What to check | Result | Note or action |
|---|---|---|---|---|
| 1 | Drawings on site | Trades are working from the current revision | ||
| 2 | Set-out | Grids, levels and openings match the drawings | ||
| 3 | Work in progress | Each trade's work matches the approved sample or first-off |
Common mistakes with inspection checklists
- Ticked from the site office. A checklist filled in from memory is a guess with a signature.
- Lines nobody can fail. 'Workmanship satisfactory' always passes. Name what you measure.
- A fail with no owner. Every fail needs a name and a date, or it is found again next week.
- One sheet for the whole floor. Inspect by room, so you can show which room was checked.
- No photos. In a dispute, a tick is your word. A photo with a location is evidence.

A phone checklist, built from your drawings
| Matrak Quality | Paper checklist | |
|---|---|---|
| Pass, fail or N/A on every line | Yes | Yes |
| A checklist for each trade and room, made from your drawings | Yes | No |
| Answered on the phone at the work | Yes | No |
| A photo kept on every check | Yes | No |
| A failed check shows on the drawing straight away | Yes | No |
| Every check filed against its room for handover | Yes | No |
How Matrak does it. Matrak Quality turns your drawings into inspection checklists for each trade and each room. The trade answers each check on the phone with a photo, a failed check marks the room on the drawing, and hold points wait for the right sign-off. $18,000 for one project for a year, 50 subcontractor companies included (A$, plus GST).
Why nobody retypes a checklist. Matrak fetches the drawings from Procore, Aconex and Autodesk and picks up each new revision, and every answer is kept in a full audit history with who gave it and when.
Weighing up inspection systems? See how the quality systems compare. Related: the construction quality management plan and the ITP template.
Frequently asked questions
What is a site inspection checklist?
It is a list of items to check on a walk of a construction site, each marked pass, fail or not applicable, with notes, photos and an action for anything that fails. It makes every inspection cover the same ground.
How often should a construction site be inspected?
Walk the whole site at least once a week, and inspect each trade's work before it starts, at the first-off and before it is covered up. Your contract or quality plan may set a tighter rhythm.
Who should carry out a site inspection?
The site manager or supervisor does the weekly walk. Each subcontractor's supervisor inspects their own work first, and the engineer, certifier or client's representative inspects the points that are theirs.
What is the difference between a site inspection checklist and an ITP?
A checklist is a list of things to look at on a walk. An ITP is the plan for one trade: every inspection and test in build order, the pass mark, who signs and where work must stop. A checklist filled in for one room is often the record an ITP asks for.
What should I do when an item fails?
Record it with a photo, name who will fix it and by when, and re-inspect before the work is covered. If it is covered up or built to the wrong drawing, raise a non-conformance report.