Construction submittals are due when the programme says: a Matrak construction schedule with each task in progress, delayed or not started, and its start and end dates

Construction submittals are the documents, samples and data a contractor sends to the design team for review before materials are ordered or made, to show that what will be built matches the contract. A free construction submittal log template is below.

What is a construction submittal outside North America? Submittal is the US and Canadian word. Australian, New Zealand and UK projects ask for the same things as shop drawings, samples and technical data for approval, often with no single name for the set.

Types of construction submittals

TypeWhat it isExample
Shop drawingsDetailed fabrication and installation drawingsStructural steel connections
Product dataManufacturer's data sheets and performance figuresA fire-rated door set
SamplesPhysical pieces that show colour, finish and qualityCarpet tile, brick, a powder coat chip
Mock-upsA built section, approved before the rest proceedsOne bay of curtain wall
Certificates and test reportsProof of complianceMill certificates, fire test reports
Closeout submittalsHandover informationWarranties, manuals, as built drawings

The specification says which of these each section needs, usually under a submittals heading at the start of the section.

Submittals in review: a Matrak drawing approvals grid of eight levels by discipline showing approved, in review and sent back against the programme line

How the submittal process works

  1. List every submittal the specification asks for, section by section. That list is the start of your submittal log.
  2. Work out the submit-by date for each one.
  3. The subcontractor or supplier prepares the submittal.
  4. The contractor reviews and stamps it first. It is the contractor's submittal, and the stamp says it has been checked against the contract and coordinated with the other trades.
  5. The architect or engineer reviews it within the time the contract allows.
  6. It comes back with an action: approved, approved as noted, revise and resubmit, or rejected.
  7. Approved items are released for purchase or fabrication, and the log is updated.

See the late approval while there is still time to fix it. Matrak Design management tracks approvals against the dates in your programme.

What goes in a submittal log

A submittal log, or submittal register, has one line per submittal and follows it from required to approved.

  • Submittal number and specification section.
  • Description and type.
  • Who is responsible for preparing it.
  • Required on site, lead time and review time.
  • Submit-by date.
  • Date submitted and date returned.
  • Action, and the revision.
  • Ball in court: who has to act next.

Submit by = required on site, less lead time, less review time. It is the one date that tells you what is urgent. Add time for one resubmission on anything complex.

Free construction submittal log template

Take our construction submittal log template for Excel. Type the date an item is needed on site, its lead time and the review time, and the submit-by date is worked out for you. Three examples are filled in. No sign-up.

Submittal noDescriptionRequired on siteLead timeReviewSubmit byAction
05 12 00-01Structural steel shop drawings1 Feb8 weeks10 days27 NovApproved as noted
08 44 13-01Curtain wall shop drawings15 Mar12 weeks14 days7 DecIn review
09 68 13-01Carpet tile sample20 Apr6 weeks10 days27 FebNot yet due

Common mistakes

  • Starting the log after the job starts. Long-lead items are late on day one.
  • Passing on a subcontractor's submittal unchecked. Your stamp says you looked.
  • Treating "approved as noted" as approved without closing the notes.
  • Slipping in a substitution. A different product needs its own request, or an RFI.
  • No dates on the log. Then everything is equally urgent.
  • No ball-in-court column. Nobody knows whose desk it is sitting on.
  • Ordering before approval. The restocking fee is yours.
  • Losing the approved copy. Site needs the stamped version: that is document control.

Approvals tracked for you

How Matrak does it. Keep your submittals in Procore or Aconex. Connect them and Matrak Design management puts every drawing approval on one grid, by level and discipline, against the date the programme needs each one. Overdue responses are chased for you by email and in the app. $350 a month, with 4 AI credits included (A$, plus GST).

Why the long-lead items arrive. Once a submittal is approved, Matrak Supply chain follows the product through ordered, made, shipped and installed. On Aconex, ask Digi through the Aconex MCP what is still in review. Matrak runs alongside Procore, Aconex and Autodesk, with a full audit history behind every status.

After approval, the product is tracked: Matrak counting products at each stage from design, ordered, made and shipped to on site and installed, beside the phone record for one facade panel

Lead times belong in your procurement schedule. In Australia the ITP is submitted for approval the same way. Compare Matrak.

Frequently asked questions

What is a construction submittal?

A construction submittal is a document, sample or piece of data that the contractor sends to the architect or engineer for review, to show that a product or detail it plans to use meets the contract documents.

What is the purpose of submittals in construction?

To let the design team confirm, before money is spent, that the products and details the contractor plans to use meet the drawings and specification. It catches a wrong product on paper instead of on site.

Who is responsible for submittals?

The contractor. Subcontractors and suppliers prepare most of them, but the contractor reviews, stamps and submits them, and tracks them on the log. The architect or engineer reviews and returns them.

What is the difference between a submittal and an RFI?

A submittal is information the contractor sends for review, to show what it plans to build. An RFI is a question the contractor asks when the documents are unclear. One offers information, the other asks for it.

What do the submittal stamps mean?

Approved, or no exceptions taken, means proceed. Approved as noted means proceed once the comments are incorporated. Revise and resubmit means fix it and send it again first. Rejected means it does not meet the contract. Exact wording varies by firm.

How long does a submittal review take?

The contract sets it. Ten working days is typical in the US, with more for complex items. Build the review time and one resubmission into your lead times.

Put this to work on your job.

Pick the modules you need, see your price and share it with whoever signs it off. No call needed.

Read enough? See it on your job.

Start free with your own company, up to 2,000 items, or build your Matrak: pick your modules and see your price. Prefer a walkthrough? Book a demo.

Free for your own company, up to 2,000 items, no card needed · Modules for one project or every project · AI Takeoff from A$89 a trade