From shop drawing to installed: Matrak counting products at each stage from design, ordered, made and shipped to on site and installed, beside the phone record for one facade panel

A shop drawing is a detailed drawing prepared by the subcontractor, fabricator or supplier that shows exactly how they will make and install their part of the building: every dimension, material, connection and fixing. Shop drawings are checked against the design before anything is made.

What is a shop drawing on a real job? The steel fabricator's connection details, the joiner's cabinet elevations, the facade contractor's panel layouts. The term is the same in Australia, the US, Canada, New Zealand and the UK, where fabrication drawings is also common. In North America, shop drawings are one kind of submittal.

Design drawings and shop drawings compared

Design drawingsShop drawings
Made byArchitect and engineersSubcontractor, fabricator or supplier
ShowsWhat is wanted: layout, sizes, performanceHow it will be made and fixed: parts, joints, tolerances
Scale1:100 or 1:50, with typical details1:20 down to full size, every unique piece
Used byEveryone, to coordinate and priceThe workshop and the installers
Checked byThe client and the authoritiesThe builder and the design team, before fabrication

What a good shop drawing carries

  • The design drawings and revisions it was drawn from.
  • Its own number and revision, so it can go on the register.
  • Every dimension needed to make the piece, with tolerances.
  • Materials, grades and finishes.
  • Fixings and connections to the work of other trades.
  • A mark for each piece that matches the mark on the piece itself.

Which trades draw them

  • Structural steel. Member sizes, connections, bolts, welds, hole positions.
  • Precast. Panel sizes, reinforcement, lifters, cast-in items.
  • Facade and glazing. Panels, frames, glass, brackets, seals.
  • Joinery. Elevations, sections, materials, hardware.
  • Reinforcement. Bar schedules and bending shapes.
  • Services. Ductwork, pipework and switchboards, coordinated with the structure.
  • Stairs, balustrades, lifts and doors.

No level waits on a drawing nobody chased. Matrak Design management tracks every drawing's approval by level and discipline.

How shop drawing review works

  1. The subcontractor prepares the shop drawings from the current design drawings, and from site measurements where built work governs.
  2. The head contractor checks them first: dimensions, clashes with other trades, the programme.
  3. The architect or engineer reviews them against the design intent.
  4. They come back stamped.
  5. Comments are picked up, and the drawings are resubmitted if the stamp says so.
  6. Only the approved revision is released to the workshop.
  7. The approved set goes on the drawing register and out to site.
Shop drawing review tracked: a Matrak drawing approvals grid of eight levels by discipline showing approved, in review and sent back against the programme line

What the stamps mean

StampMeaningFabricate?
Approved, or no exceptions takenConforms to the design intentYes
Approved as notedConforms once the marked comments are picked upYes
Revise and resubmitDoes not conform yet: fix it and send it againNo
RejectedNot what was specifiedNo

The wording varies between firms. A designer's review is usually for general conformance with the design intent only. It does not move responsibility for dimensions, quantities or fit away from the subcontractor, unless the contract says so. File the stamped copy: it is the only revision the workshop and the site should hold.

Allow time for approval

Work backwards from the day the item is needed on site: fabrication lead time, plus review time, plus one resubmission. Structural steel needed on 1 February, with 8 weeks to fabricate and 10 days to review, has to be submitted by late November. Miss that and the crane waits. A procurement schedule sets these dates for every long-lead item.

Common mistakes

  • Drawn from a superseded design revision. The most expensive one.
  • Fabricating on "approved as noted" without picking up the notes.
  • Passed on unchecked. The head contractor's check is where clashes get caught.
  • No coordination between trades. The duct that meets the beam.
  • Site dimensions not checked for work that has to fit what is already built.
  • A design change hidden in a shop drawing. A change needs an RFI or a variation, not a quiet redraw.
  • Reviews with no deadline.

From shop drawing to installed

How Matrak does it. Shop drawings are still submitted and stamped in Procore or Aconex. Connect them and Matrak Design management tracks every approval by level and discipline, against the date the programme needs it, and chases overdue responses by email and in the app. $350 a month, with 4 AI credits included (A$, plus GST).

Why fabrication starts on time. After approval, Matrak Supply chain tracks every product from shop drawing to installed, with one QR code per product. On Aconex, ask Digi through the Aconex MCP which shop drawings are still in review. Matrak connects to Procore, Aconex and Autodesk and keeps a full audit history.

After the shop drawings are approved: a Matrak production report counting facade panels, bathroom pods, windows and joinery at each step from cut and assemble to QA, packed and dispatched, beside the phone record

When the job is finished, the approved shop drawings feed the as built drawings. Compare Matrak.

Frequently asked questions

What is a shop drawing?

A shop drawing is a drawing produced by a subcontractor, fabricator or supplier that shows in detail how a component will be manufactured, assembled and installed. It is reviewed against the design drawings before fabrication starts.

Who prepares shop drawings?

The subcontractor, fabricator, manufacturer or supplier responsible for the item, or a detailer working for them. They know how their product is made, so they draw it.

Who approves shop drawings?

The head contractor checks them first, then the architect or the relevant engineer reviews them for conformance with the design. The contract sets out who reviews what, and how long they have.

What is the difference between shop drawings and as built drawings?

Shop drawings are made before fabrication and show how a part will be made and fitted. As built drawings are finished after construction and show what was actually built, including changes made on site.

How long does shop drawing review take?

The contract or specification sets it, commonly 10 working days for each review. Allow for at least one resubmission when you plan lead times.

Are shop drawings contract documents?

Usually not. Under most standard contracts they show how the contractor proposes to meet the contract documents and do not change them. If a shop drawing departs from the design, the departure has to be flagged and approved in writing.

Put this to work on your job.

Pick the modules you need, see your price and share it with whoever signs it off. No call needed.

Read enough? See it on your job.

Start free with your own company, up to 2,000 items, or build your Matrak: pick your modules and see your price. Prefer a walkthrough? Book a demo.

Free for your own company, up to 2,000 items, no card needed · Modules for one project or every project · AI Takeoff from A$89 a trade