A shop drawing is a detailed drawing prepared by the subcontractor, fabricator or supplier that shows exactly how they will make and install their part of the building: every dimension, material, connection and fixing. Shop drawings are checked against the design before anything is made.
What is a shop drawing on a real job? The steel fabricator's connection details, the joiner's cabinet elevations, the facade contractor's panel layouts. The term is the same in Australia, the US, Canada, New Zealand and the UK, where fabrication drawings is also common. In North America, shop drawings are one kind of submittal.
Design drawings and shop drawings compared
| Design drawings | Shop drawings | |
|---|---|---|
| Made by | Architect and engineers | Subcontractor, fabricator or supplier |
| Shows | What is wanted: layout, sizes, performance | How it will be made and fixed: parts, joints, tolerances |
| Scale | 1:100 or 1:50, with typical details | 1:20 down to full size, every unique piece |
| Used by | Everyone, to coordinate and price | The workshop and the installers |
| Checked by | The client and the authorities | The builder and the design team, before fabrication |
What a good shop drawing carries
- The design drawings and revisions it was drawn from.
- Its own number and revision, so it can go on the register.
- Every dimension needed to make the piece, with tolerances.
- Materials, grades and finishes.
- Fixings and connections to the work of other trades.
- A mark for each piece that matches the mark on the piece itself.
Which trades draw them
- Structural steel. Member sizes, connections, bolts, welds, hole positions.
- Precast. Panel sizes, reinforcement, lifters, cast-in items.
- Facade and glazing. Panels, frames, glass, brackets, seals.
- Joinery. Elevations, sections, materials, hardware.
- Reinforcement. Bar schedules and bending shapes.
- Services. Ductwork, pipework and switchboards, coordinated with the structure.
- Stairs, balustrades, lifts and doors.
No level waits on a drawing nobody chased. Matrak Design management tracks every drawing's approval by level and discipline.
How shop drawing review works
- The subcontractor prepares the shop drawings from the current design drawings, and from site measurements where built work governs.
- The head contractor checks them first: dimensions, clashes with other trades, the programme.
- The architect or engineer reviews them against the design intent.
- They come back stamped.
- Comments are picked up, and the drawings are resubmitted if the stamp says so.
- Only the approved revision is released to the workshop.
- The approved set goes on the drawing register and out to site.

What the stamps mean
| Stamp | Meaning | Fabricate? |
|---|---|---|
| Approved, or no exceptions taken | Conforms to the design intent | Yes |
| Approved as noted | Conforms once the marked comments are picked up | Yes |
| Revise and resubmit | Does not conform yet: fix it and send it again | No |
| Rejected | Not what was specified | No |
The wording varies between firms. A designer's review is usually for general conformance with the design intent only. It does not move responsibility for dimensions, quantities or fit away from the subcontractor, unless the contract says so. File the stamped copy: it is the only revision the workshop and the site should hold.
Allow time for approval
Work backwards from the day the item is needed on site: fabrication lead time, plus review time, plus one resubmission. Structural steel needed on 1 February, with 8 weeks to fabricate and 10 days to review, has to be submitted by late November. Miss that and the crane waits. A procurement schedule sets these dates for every long-lead item.
Common mistakes
- Drawn from a superseded design revision. The most expensive one.
- Fabricating on "approved as noted" without picking up the notes.
- Passed on unchecked. The head contractor's check is where clashes get caught.
- No coordination between trades. The duct that meets the beam.
- Site dimensions not checked for work that has to fit what is already built.
- A design change hidden in a shop drawing. A change needs an RFI or a variation, not a quiet redraw.
- Reviews with no deadline.
From shop drawing to installed
How Matrak does it. Shop drawings are still submitted and stamped in Procore or Aconex. Connect them and Matrak Design management tracks every approval by level and discipline, against the date the programme needs it, and chases overdue responses by email and in the app. $350 a month, with 4 AI credits included (A$, plus GST).
Why fabrication starts on time. After approval, Matrak Supply chain tracks every product from shop drawing to installed, with one QR code per product. On Aconex, ask Digi through the Aconex MCP which shop drawings are still in review. Matrak connects to Procore, Aconex and Autodesk and keeps a full audit history.

When the job is finished, the approved shop drawings feed the as built drawings. Compare Matrak.
Frequently asked questions
What is a shop drawing?
A shop drawing is a drawing produced by a subcontractor, fabricator or supplier that shows in detail how a component will be manufactured, assembled and installed. It is reviewed against the design drawings before fabrication starts.
Who prepares shop drawings?
The subcontractor, fabricator, manufacturer or supplier responsible for the item, or a detailer working for them. They know how their product is made, so they draw it.
Who approves shop drawings?
The head contractor checks them first, then the architect or the relevant engineer reviews them for conformance with the design. The contract sets out who reviews what, and how long they have.
What is the difference between shop drawings and as built drawings?
Shop drawings are made before fabrication and show how a part will be made and fitted. As built drawings are finished after construction and show what was actually built, including changes made on site.
How long does shop drawing review take?
The contract or specification sets it, commonly 10 working days for each review. Allow for at least one resubmission when you plan lead times.
Are shop drawings contract documents?
Usually not. Under most standard contracts they show how the contractor proposes to meet the contract documents and do not change them. If a shop drawing departs from the design, the departure has to be flagged and approved in writing.