As built drawings are the construction drawings marked up to show what was actually built: every change from the design in position, size, route, level or material, recorded as the work went in. They go to the owner at completion, so the next person to cut, drill or extend knows what is really behind the wall.
Also written as-built drawings, and called as-constructed drawings on Australian civil work. Redline drawings are the marked-up site set they are made from. The meaning is the same in Australia, the US, Canada, New Zealand and the UK.
What as built drawings must show
- Changes in position or size. A wall moved, a door rehung, a column made bigger.
- Hidden routes and depths. In-ground services, conduits in slabs, pipework in risers and ceilings.
- Changes of material or product, with the approved substitution.
- Where each change came from. The RFI, site instruction or variation number beside it.
- Levels and set-out as surveyed, not as designed.
- Date, name and status. Who recorded it, when, and "as built" in the title block with a revision.

Who makes them, and when
| Who | What they do |
|---|---|
| Each subcontractor | Marks up their own trade's drawings as the work is installed |
| Head contractor | Keeps the master redline set, checks the trades' mark-ups and compiles the final set |
| Surveyor | Surveys in-ground services, levels and set-out where the contract asks |
| Design consultants | Often redraw the mark-ups as clean record drawings in CAD or the model |
| Owner or facility manager | Receives them with the operation and maintenance manuals at handover |
The when matters more than the who. Marked on the day, a change takes two minutes. Rebuilt from memory at handover, it takes weeks and is often wrong. Write the format and the due date into every subcontract, so the mark-ups arrive without a fight.
As built, record and shop drawings compared
| Drawing | Made by | Shows |
|---|---|---|
| Design drawings, for construction | Architect and engineers | What is to be built |
| Shop drawings | Subcontractor or fabricator | How one trade will make and fit its part |
| Redline or as built drawings | Contractor and subcontractors | What was built, marked up on site |
| Record drawings | Usually the designer | The as built mark-ups, redrawn cleanly |
Some contracts use as built and record drawings to mean the same thing. Check which yours asks for, in what format, and who signs them.
Nobody builds off the old drawing. Matrak Revisions compares each new revision with the last and marks what changed.
As built drawings checklist
- One redline set for each trade, kept on site from day one.
- Mark each change the day it happens, in red, with a date and initials.
- Photograph anything about to be covered, with a tape in the shot.
- Write the RFI, instruction or variation number beside each change.
- Survey in-ground services before backfill.
- Collect each subcontractor's redlines when their work on a level finishes, not when they leave site.
- Strike through the superseded design. Do not erase it.
- Review the redlines every month, not at the end.
- Final set: every sheet marked as built, dated, with the design revision it started from.
Common mistakes
- Left to the last week. The people who knew have left the job.
- Marked up on an old revision. Start from the latest one on the drawing register.
- "No change" on every sheet. Stamped without anyone checking.
- Hidden services drawn where they were designed, not where they were laid.
- Only the architecturals updated. The services drawings are what the owner needs most.
- Photos with no location. A pipe in a trench could be anywhere.
As built records without the scramble
How Matrak does it. As builts go wrong when site works from one revision and the record is kept on another. Matrak Revisions overlays each new revision on the last and marks what changed, so the set on site and the set being marked up match. Revisions is $400 a month, with 5 comparisons included (A$, plus GST).
Why handover is quicker. Sheets are read straight from Procore, Aconex and Autodesk, with nothing to download or upload. Install progress is logged on the drawing with a photo on every item, and the full audit history says who recorded what and when, long before anyone asks for the as built set.

As built drawings are usually due at practical completion and get used all through the defects liability period. More on keeping the set straight: document control in construction. Compare Matrak.
Frequently asked questions
What are as built drawings?
As built drawings are the project drawings updated to show what was actually constructed, including every change made during the build. They are handed to the owner at completion as the record of the finished building.
Who is responsible for as built drawings?
The contractor, under most contracts. Each subcontractor marks up its own trade, the head contractor compiles and checks the set, and the designers may redraw it as record drawings. The contract says who does what, and in which format.
What is the difference between as built drawings and record drawings?
As built drawings are the contractor's marked-up set showing what was built. Record drawings are usually the designer's clean redraw of those mark-ups. Some contracts use the two terms for the same thing.
Are as built drawings required for practical completion?
Often, yes. Many contracts list as built drawings, manuals and warranties among the documents due at or before practical completion, and some hold back money until they arrive. Check the handover clause in yours.
What format should as built drawings be in?
Whatever the contract specifies: commonly PDF plus the native CAD files, and on some projects an updated model. Agree the format, the layers and the file naming at the start, not at handover.
How accurate do as built drawings need to be?
Accurate enough for someone to find and work on what is hidden. For in-ground services many contracts require a survey to a stated tolerance. For everything else, record real dimensions and offsets from fixed points instead of scaling off the drawing.